Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

ZEST

by BSR PROJECTS · 60 homes · 0.35 acres · 1 tower · Bengaluru East

Past due, no completion filed Past its deadline of 15 Mar 2022, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 15 Mar 2022, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
172 homes per acre

Similar projects across the city: 76 per acre. 45% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?2 due so far
0% on time

Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed, 2 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started5 Dec 2018
  2. Approved by RERA9 Aug 2019
  3. First promised15 Jun 2021

    The date the builder gave at registration.

  4. Deadline (extended)15 Mar 2022

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

1BHK
320 sq ft
30 m² carpet · sizes 250–360 sq ft (36 at this size)
21 m² land share · 4 m² balcony/terrace · 1 parking space
60 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower -12 floors

Tower -1: 60 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project172
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project45%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.35 acres

1,416 m²

Ground covered by buildings
55% of the land

777 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 4 RERA projects of BSR PROJECTS on the map

The company

Registered as
BSR PROJECTS
Type
Partnership Firm
PAN
AAOFB7884R

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹75.0 lakh
Construction
₹8.2 cr
Total project cost
₹13.2 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.