RERA project · Residential/Group Housing

WORLD OF GARDENS

by RLP TRENDSQUARES PROJECTS PRIVATE LIMITED · 648 homes · 11.68 acres · 4 towers · Bengaluru East

Upcoming Under construction, due Sep 2030. 23% built with 21% of the time used. 24% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
23% built

Due 30 Sep 2030. 21% of the time from RERA approval to the deadline has passed.

Built23%
Time used21%
How much is sold?491 left
24% booked

157 of 648 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
56 homes per acre

Similar projects within 3 km: 80 per acre. 93% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started10 Sep 2025
  2. Approved by RERA30 Sep 2025
  3. Today24 Oct 2026

    21% of the time to the deadline has passed.

  4. If it slips like a typical project2 Jul 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2612%
Q4 2025-2623%
Q1 2026-2716%
Q2 2026-2723%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower 125%
Tower 222%
Tower 323%
Tower 424%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

157 booked491 leftQ2 2026-27

Still available: 109 × 3.5 BHK, 114 × 4 BHK, 268 × 3 BHK.

Booked, by type

3.5 BHK35 of 144
4 BHK30 of 144
3 BHK92 of 360

Booked, each quarter

Q3 2025-2689 of 648
Q4 2025-26115 of 648
Q1 2026-27133 of 648
Q2 2026-27157 of 648

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
  • 1,210 sq ft144 homes112.4 m²
  • 1,083 sq ft72 homes100.6 m²
  • 1,161 sq ft72 homes107.9 m²
  • 1,183 sq ft72 homes109.9 m²
Typically 44 m² land share · 12 m² balcony/terrace · 1 parking space
360 homes · 56% of the project
4 BHK
  • 1,411 sq ft144 homes131.1 m²
Typically 53 m² land share · 15 m² balcony/terrace · 1 parking space
144 homes · 22% of the project
3.5 BHK
  • 1,280 sq ft72 homes118.9 m²
  • 1,288 sq ft72 homes119.7 m²
Typically 48 m² land share · 12 m² balcony/terrace · 1 parking space
144 homes · 22% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower 135 floors
Tower 235 floors
Tower 335 floors
Tower 435 floors

Tower 1: 144 homes, 112 m tall, 2 basements · Tower 2: 144 homes, 112 m tall, 2 basements · Tower 3: 180 homes, 112 m tall, 2 basements · Tower 4: 180 homes, 112 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project56
Typical within 3 km (97)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project93%
Typical within 3 km (99)52%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
11.68 acres

47,284 m²

Ground covered by buildings
7% of the land

3,400 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.10 per home

714 covered, 0 open

Built-up area, all floors
17,07,703 sq ft

1,58,651 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
RLP TRENDSQUARES PROJECTS PRIVATE LIMITED
Type
Company
Company number
U68100KA2023PTC172376

CIN or LLPIN, from the Registrar of Companies.

PAN
AAMCR5968H
GSTIN
29AAMCR5968H1ZK

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹30.0 crBuilding and development ₹674.9 crTotal ₹704.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹11.1 cr₹63.7 cr
Q4 2025-26₹30.3 cr₹30.3 cr
Q1 2026-27₹62.8 cr₹62.5 cr
Q2 2026-27₹27.9 cr₹28.1 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.77 kmReliable
  • Nearest railway station2.9 kmReliable
  • Bus stops within 500 m1Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km1Caveat
  • Nearest lake / water body (≥2 ha)0.84 kmCaveat

Hospitals

  • Nearest hospital1.64 kmCaveat

Schools

  • Schools in pincode 560066 (UDISE+ census)44Caveat
  • Median pupil-teacher ratio, schools within 1 km16.8 :1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKadugodi PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km8Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.68 kmReliable
  • Nearest sewage treatment plant1.32 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)7.89 kmCaveat
  • Nearest commercial-airport runway20.57 kmReliable
  • Distance to runway approach-path proxy19.75 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.00349, 77.73569), 2026-10-24. Each figure's source and caveat are in the full report.