Delivered late Completed: the builder filed for completion on 18 Aug 2020, 231 days after the date it first promised.
At a glance
The builder filed for completion on 18 Aug 2020, 231 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 84% of the land is left open.
Complaints to RERA about this project. 6 more about the builder's other projects.
The RERA page doesn't say.
Of its 8 RERA projects in Bengaluru Urban: 2 delivered on time, 2 late (after the date first promised), 4 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started16 May 2017
- Approved by RERA12 Sep 2017
- Completion filed18 Aug 2020
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 1,551 sq ft75 homes144.1 m²
- 1,181 sq ft49 homes109.7 m²
- 1,194 sq ft25 homes110.9 m²
- 1,176 sq ft24 homes109.3 m²
- 1,791 sq ft25 homes166.4 m²
- 165 sq ft25 homes15.3 m²
- 1,176 sq ft1 home109.3 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
T@: 224 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 2.89 acres
- Ground covered by buildings
- 16% of the land
11,698 m²
1,887 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 8 RERA projects of Mahindra Lifespaces on the map
Complaints to RERA about its other projects
- Windchimes Phase 1 6 complaints
The company
- Registered as
- Mahindra Homes Private Limited
- Type
- Company
- Company number
- U70102MH2010PTC203618
- PAN
- AAACW9691A
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/170912/000495 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Grant of time 27 Apr 2019 · Disposed Ao
Documents
49 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹77.9 cr
- Construction
- ₹206.8 cr
- Total project cost
- ₹284.7 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.