Vista Svara

by Vista Spaces Sun (Lalbagh) Private Limited · 36 homes · 0.48 acres · 1 tower · Bengaluru South

Upcoming Under construction, due Oct 2026. 81% built with 100% of the time used. 50% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
81% built

Due 30 Oct 2026. 100% of the time from RERA approval to the deadline has passed.

Built81%
Time used100%
How much is sold?16 left
50% booked

16 of 32 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
76 homes per acre

Similar projects within 3 km: 55 per acre. 76% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started4 Jan 2022
  2. Approved by RERA13 Jul 2022
  3. Today24 Oct 2026

    100% of the time to the deadline has passed.

  4. If it slips like a typical project1 Aug 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2672%
Q4 2025-2677%
Q1 2026-2778%
Q2 2026-2781%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

16 booked16 leftQ2 2026-27

Still available: 5 × 2bhk, 7 × 3bhk, 4 × 4bhk.

Booked, by type

2bhk3 of 8
3bhk9 of 16
4bhk4 of 8

Booked, each quarter

Q3 2025-2610 of 32
Q4 2025-2613 of 32
Q1 2026-2713 of 32
Q2 2026-2716 of 32

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3bhk
  • 950 sq ft7 homes88.3 m²
  • 1,074 sq ft7 homes99.8 m²
  • 935 sq ft1 home86.9 m²
  • 1,054 sq ft1 home97.9 m²
Typically 57 m² land share · 15 m² balcony/terrace · 1 parking space
16 homes · 50% of the project
4bhk
  • 1,370 sq ft7 homes127.3 m²
  • 1,326 sq ft1 home123.2 m²
Typically 80 m² land share · 15 m² balcony/terrace · 1 parking space
8 homes · 25% of the project
2bhk
  • 739 sq ft7 homes68.7 m²
  • 713 sq ft1 home66.2 m²
Typically 43 m² land share · 10 m² balcony/terrace · 1 parking space
8 homes · 25% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower 18 floors

Tower 1: 32 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project76
Typical within 3 km (23)55
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project76%
Typical within 3 km (25)52%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.48 acres

1,930 m²

Ground covered by buildings
25% of the land

474 m²

Floor-area ratio
2.50

Floors built per unit of land: 2.50 m² of floors for each m² of land.

Parking
1.00 per home

10 covered, 26 open

Built-up area, all floors
60,461 sq ft

5,617 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
Vista Spaces Sun (Lalbagh) Private Limited
Type
Company
Company number
U45500KA2018PTC111585

CIN or LLPIN, from the Registrar of Companies.

PAN
AAGCV3499P
GSTIN
29AAGCV3499P1Z7
Website
www.vistaspaces.in

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹24.8 crBuilding and development ₹27.0 crTotal ₹51.8 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹62.4 lakh₹44.0 lakh
Q4 2025-26₹3.5 cr₹2.4 cr
Q1 2026-27₹1.7 cr₹1.2 cr
Q2 2026-27₹32.4 lakh₹4.5 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.32 kmReliable
  • Nearest railway station2.83 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km9Caveat
  • Nearest lake / water body (≥2 ha)1.42 kmCaveat

Hospitals

  • Nearest hospital0.34 kmCaveat

Schools

  • Schools in pincode 560027 (UDISE+ census)44Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km13Caveat
  • Median pupil-teacher ratio, schools within 1 km13.5 :1Caveat
  • Schools with library + playground + ICT lab (1 km)5Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionWilsongarden PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)32 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km6Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well9.5 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)9.69 kmReliable
  • Nearest sewage treatment plant0.52 kmCaveat
  • Industrial zones within 1 km8Caveat
  • Nearest airfield runway (any, incl. military)7.41 kmCaveat
  • Nearest commercial-airport runway27.88 kmReliable
  • Distance to runway approach-path proxy24.3 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.95878, 77.58661), 2026-10-24. Each figure's source and caveat are in the full report.