RERA project · Plotted Development
Vaishnavi Railways Enclave
by SEVEN HILLS DEVELOPERS AND TRADERS PRIVATE LIMITED · 81 plots · 5.47 acres · Anekal
Past due, no completion filed Past its deadline of 5 Apr 2023, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 5 Apr 2023, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 16 per acre. 45% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Apr 2022
- Approved by RERA18 Nov 2022
- Deadline5 Apr 2023
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.47 acres
- Plot area (the sites)
- 55% of the land
- Roads
- 6,743 m²
- Parks and open spaces
- 2,216 m²
- Civic amenity sites
- 11,290 m²
22,156 m²
12,089 m²
Sites kept for public uses such as a school or a health centre.
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- SEVEN HILLS DEVELOPERS AND TRADERS PRIVATE LIMITED
- Type
- Company
- Company number
- U07010KA2005PTC035662
- GSTIN
- 29AAKCS6529B1Z6
CIN or LLPIN, from the Registrar of Companies.
The land is owned together with others (a joint development), including RAILWAY EMPLOYEES CO-OPERATIVE HOUSING SOCIETY LIMITED, SEVENHILLS DEVELOPERS AND TRADERS PRIVATE LIMITED.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/181122/005462 · Approved
- Building plan approvedLocal Planing Authority · 2AO/65/2020-2021 · 9 Jul 2021
- Litigation on the landNone declared
- Litigation on the projectNot stated
- Water sourceLocal Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
178 files on the RERA page: Approved plan ↗, Commencement certificate ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
CaveatCost as certified by the builder's chartered accountant at registration.