RERA project · Residential/Group Housing

VAISHNAVI AT-ONE KRISHNA BRINDAVAN

by VAISHNAVI AT-ONE INFRASTRUCTURE LLP · 359 homes · 4.92 acres · 2 towers · Bengaluru South

Upcoming Under construction, due Jun 2030. 28% built with 22% of the time used. 48% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
28% built

Due 20 Jun 2030. 22% of the time from RERA approval to the deadline has passed.

Built28%
Time used22%
How much is sold?188 left
48% booked

171 of 359 homes, as the builder reported for Q2 2026-27.

How crowded is it?About the same
73 homes per acre

Similar projects within 3 km: 73 per acre. 52% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?1 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Sep 2025
  2. Approved by RERA8 Oct 2025
  3. Today24 Oct 2026

    22% of the time to the deadline has passed.

  4. If it slips like a typical project22 Mar 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2619%
Q4 2025-2622%
Q1 2026-2725%
Q2 2026-2728%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower A28%
B28%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

171 booked188 leftQ2 2026-27

Still available: 4 × 2 BHK, 124 × 3 BHK, 60 × 4 BHK.

Booked, by type

2 BHK0 of 4
3 BHK112 of 236
4 BHK59 of 119

Booked, each quarter

Q3 2025-2691 of 359
Q4 2025-26133 of 359
Q1 2026-27153 of 359
Q2 2026-27171 of 359

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,319 sq ft
122 m² carpet · sizes 1,209–1,663 sq ft (116 at this size)
52 m² land share · 9 m² balcony/terrace · 1 parking space
236 homes · 66% of the project
4 BHK
1,663 sq ft
154 m² carpet
64 m² land share · 11 m² balcony/terrace · 1 parking space
119 homes · 33% of the project
2 BHK
1,008 sq ft
94 m² carpet
39 m² land share · 5 m² balcony/terrace · 1 parking space
4 homes · 1% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A32 floors
B31 floors

Tower A: 183 homes, 107 m tall, 1 basement · B: 176 homes, 104 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project73
Typical within 3 km (38)73
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project52%
Typical within 3 km (38)54%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.92 acres

19,930 m²

Ground covered by buildings
48% of the land

9,482 m²

Floor-area ratio
3.24

Floors built per unit of land: 3.24 m² of floors for each m² of land.

Parking
1.89 per home

667 covered, 12 open

Built-up area, all floors
10,62,020 sq ft

98,665 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of Vaishnavi AT-One Infrastructure LLP on the map

The company

Registered as
VAISHNAVI AT-ONE INFRASTRUCTURE LLP
Type
Partnership Firm
PAN
AATFV4523A
GSTIN
29AATFV4523A1Z0
Website
www.vaishnavigroup.com

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹162.1 crBuilding and development ₹471.4 crTotal ₹633.5 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹34.9 cr₹25.0 cr
Q4 2025-26₹91.9 cr₹61.5 cr
Q1 2026-27₹136.9 cr₹95.8 cr
Q2 2026-27₹198.1 cr₹137.6 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.65 kmReliable
  • Nearest railway station6.06 kmReliable
  • Bus stops within 500 m8Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km17Caveat
  • Nearest lake / water body (≥2 ha)1.4 kmCaveat

Hospitals

  • Nearest hospital0.37 kmCaveat

Schools

  • Schools in pincode 560078 (UDISE+ census)117Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km18Caveat
  • Median pupil-teacher ratio, schools within 1 km18.6 :1Caveat
  • Schools with library + playground + ICT lab (1 km)6Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKumaraswamy Layout PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)29 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km3Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.87 kmReliable
  • Nearest sewage treatment plant1.83 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)10.18 kmCaveat
  • Nearest commercial-airport runway33.48 kmReliable
  • Distance to runway approach-path proxy29.8 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.91124, 77.56847), 2026-10-24. Each figure's source and caveat are in the full report.