RERA project · Plotted Development
Trilok Villas and Apartments
by NARESH KUMAR H · 103 plots · 6.49 acres · Bengaluru South
Delivered on time Completed: the builder filed for completion on 26 Apr 2023, by the date it promised.
At a glance
The builder filed for completion on 26 Apr 2023, by the date it promised.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 16 per acre. 46% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 2 RERA projects in Bengaluru Urban: 2 delivered on time.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started15 Sep 2022
- Approved by RERA19 Dec 2022
- Completion filed26 Apr 2023
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 6.49 acres
- Plot area (the sites)
- 54% of the land
- Roads
- 8,037 m²
- Parks and open spaces
- 4,023 m²
26,253 m²
14,078 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of NARESH KUMAR H on the map
The company
- Registered as
- NARESH KUMAR H
- Type
- Proprietorship Firm
Its other registrations on RERA Karnataka
- Trilok Premium Apartments PRM/KA/RERA/1251/310/PR/090925/008077 · approved 9 Sep 2025
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/191222/005541 · Approved
- Building plan approvedBDA - Bangalore Development Authority · BDA/TPM/PRL-40/2021-22/1399/2022-23 · 15 Sep 2022
- Litigation on the landNone declared
- Litigation on the projectNot stated
- Water sourceBoreWell,BWSSB
Complaints to RERA about this project
None on RERA Karnataka.
Documents
297 files on the RERA page: Approved plan ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station0.99 kmReliable
- Nearest railway station2.24 kmReliable
- Bus stops within 500 m3Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km6Caveat
- Nearest lake / water body (≥2 ha)0.63 kmCaveat
Hospitals
- Nearest hospital0.75 kmCaveat
Schools
- Schools in pincode 560059 (UDISE+ census)12Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
- Schools with library + playground + ICT lab (1 km)2Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionRajarajeshwari Nagar PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)11 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km5Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km2Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)14.35 kmReliable
- Nearest sewage treatment plant1.69 kmCaveat
- Industrial zones within 1 km8Caveat
- Nearest airfield runway (any, incl. military)16.12 kmCaveat
- Nearest commercial-airport runway35.21 kmReliable
- Distance to runway approach-path proxy30.08 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.92647, 77.50723), 2026-10-24. Each figure's source and caveat are in the full report.