RERA project · Plotted Development
TRIFECTA VERDE EN RESPLANDOR VILLA PHASE 3
by TRIFECTA PROJECTS PRIVATE LIMITED · 158 plots · 10.52 acres · Bengaluru East
Upcoming Under construction, due Dec 2027. 98% built with 61% of the time used.
At a glance
Due 9 Dec 2027. 61% of the time from RERA approval to the deadline has passed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 18 per acre. 45% of the land is left open.
Complaints to RERA about this project. 2 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 6 RERA projects in Bengaluru Urban: 2 delivered on time, 4 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started10 Dec 2024
- Approved by RERA23 Jan 2025
- Today24 Oct 2026
61% of the time to the deadline has passed.
- Deadline9 Dec 2027
The date it must be complete by.
- If it slips like a typical project9 Sep 2028
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 10.52 acres
- Plot area (the sites)
- 55% of the land
- Roads
- 12,508 m²
- Parks and open spaces
- 4,270 m²
- Civic amenity sites
- 2,474 m²
42,593 m²
23,342 m²
Sites kept for public uses such as a school or a health centre.
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 6 RERA projects of TRIFECTA PROJECTS PRIVATE LIMITED on the map
Complaints to RERA about its other projects
- TRIFECTA VERDE EN RESPLANDOR PHASE 1 1 complaint
- TRIFECTA VERDE ENRESPLANDOR VILLA PHASE-2 1 complaint
The company
- Registered as
- TRIFECTA PROJECTS PRIVATE LIMITED
- Type
- Company
- Company number
- U45200KA2012PTC062831
- PAN
- AACCE9717F
- GSTIN
- 29AACCE9717F1ZG
- Website
- https://trifectaprojects.com/
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
10 registrations under this company
- Trifecta Veranza PRM/KA/RERA/1251/308/PR/210126/008418 · approved 21 Jan 2026
- TRIFECTA VANTO PHASE-2 PRM/KA/RERA/1251/310/PR/250625/007871 · approved 25 Jun 2025
- TRIFECTA VANTO PHASE-1 PRM/KA/RERA/1251/446/PR/190424/006813 · approved 19 Apr 2024
- TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3 PRM/KA/RERA/1251/446/PR/060424/006778 · approved 6 Apr 2024
- TRIFECTA RETTO PRM/KA/RERA/1251/310/PR/060423/005849 · approved 6 Apr 2023
- TRIFECTA VERDE ENRESPLANDOR VILLA PHASE-2 PRM/KA/RERA/1250/304/PR/101122/005447 · approved 10 Nov 2022
- TRIFECTA VERDE EN RESPLANDOR ROW HOUSE PHASE-2 PRM/KA/RERA/1250/304/PR/200922/005254 · approved 20 Sep 2022
- TRIFECTA VERDE EN RESPLANDOR PHASE 1 PRM/KA/RERA/1250/304/PR/210319/004025 · approved 19 Mar 2021
- TRIFECTA BUENO PRM/KA/RERA/1251/446/PR/210129/003798 · approved 29 Jan 2021
- Trifecta Verde En Resplendor PRM/KA/RERA/1250/304/PR/200323/003374 · approved 23 Mar 2020
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/230125/007422 · Approved
- Building plan approvedHoskote Planning Authority · HPA/LAO/07/2022-23 · 12 Sep 2024
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBoreWell
Complaints to RERA about this project
None on RERA Karnataka.
Documents
213 files on the RERA page.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹28.6 cr | ₹6.9 cr |
| Q4 2025-26 | ₹21.4 cr | ₹21.4 cr |
| Q1 2026-27 | ₹14.9 cr | ₹14.9 cr |
| Q2 2026-27 | ₹22.6 cr | ₹22.6 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station12.45 kmReliable
- Nearest railway station12.41 kmReliable
- Bus stops within 500 m1Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km0Caveat
- Nearest lake / water body (≥2 ha)1.07 kmCaveat
Hospitals
- Nearest hospital3.32 kmCaveat
Schools
- Schools in pincode 560049 (UDISE+ census)110Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionAvalahally PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)3.68 kmReliable
- Nearest sewage treatment plant5.28 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)9.34 kmCaveat
- Nearest commercial-airport runway9.34 kmReliable
- Distance to runway approach-path proxy8.06 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat
ReliableFrom our location report at the builder-entered pin (13.10815, 77.75070), 2026-10-24. Each figure's source and caveat are in the full report.