RERA project · Residential/Group Housing
Thirumala lakshmi vaibav
by Sri Chowdeshwari Projects · 205 homes · 3.10 acres · 4 towers · Bengaluru East
Upcoming Under construction, due Dec 2026, after an extension. 99% built with 98% of the time used. 52% of homes booked.
At a glance
Due 31 Dec 2026. 98% of the time from RERA approval to the deadline has passed.
107 of 205 homes, as the builder reported for Q2 2026-27.
Similar projects across the city: 76 per acre. 52% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started24 Oct 2014
- Approved by RERA20 Apr 2018
- First promised29 Nov 2019
The date the builder gave at registration.
- Today24 Oct 2026
98% of the time to the deadline has passed.
- Deadline (extended)31 Dec 2026
The date it must be complete by.
- If it slips like a typical project2 Oct 2027
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 98 × 3 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Narayanadri: 40 homes, 1 basement · Vishabadri: 40 homes, 1 basement · Garudadri: 80 homes, 1 basement · Anjanadri: 45 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.10 acres
- Ground covered by buildings
- 175% of the land
12,545 m²
21,948 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Sri Chowdeshwari Projects
- Type
- Partnership Firm
- PAN
- ABTFS0803K
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/180420/001496 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q2 2026-27 update
Complaints to RERA about this project
- Refund for stoppage of work along with interest and compensation 8 Aug 2019 · Disposed Authority
- Refund of amounts paid with interest&Compensation 29 Aug 2019 · Disposed Ao
- Refund of earnest money of Rs. 26,51,975/-remitted for Flat No. 402, in Block -1 (Garudadri Block), with interest 18% PA and delay compensation Rs. 3,04,920/- with interest 18% PA & cost of litigation 4 Sep 2019 · Disposed Ao
- Refund of amount and Compensation due to pending Construction, non-delivery and breach of agreement 10 Mar 2022 · Disposed Authority Bench5
- Seeking Refund of amount paid to the builder with interest and compensation on the account of non-completion of project and failure to deliver possession within the specified time as per agreement 9 Jan 2023 · Disposed Authority Bench5
- REFUND OF THE AMOUNT PAID TO DEVELOPER AND AMOUNT PAID TO BANK TOWARDS EMI 26 Dec 2025 · Disposed Authority Bench5
Documents
65 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹58.0 cr
- Construction
- ₹48.7 cr
- Total project cost
- ₹106.6 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹34.7 cr | ₹34.7 cr |
| Q4 2025-26 | ₹47.4 cr | ₹46.8 cr |
| Q1 2026-27 | ₹64.2 cr | ₹64.1 cr |
| Q2 2026-27 | ₹107.5 cr | ₹106.0 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.