RERA project · Plotted Development
The Woods Of East
by Odion Builders & Developers · 10.79 acres · Anekal
Delivered late Completed: the builder filed for completion on 20 Jun 2023, 1,937 days after the date it first promised.
At a glance
The builder filed for completion on 20 Jun 2023, 1,937 days after the date it first promised.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 6 RERA projects in Bengaluru Urban: 4 delivered on time, 2 late (after the date first promised).
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started1 Oct 2017
- Approved by RERA30 Jan 2018
- Completion filed20 Jun 2023
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 10.79 acres
- Plot area (the sites)
- 55% of the land
43,655 m²
24,010 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 6 RERA projects of M/s ODION BUILDERS AND DEVELOPERS on the map
The company
- Registered as
- Odion Builders & Developers
- Type
- Partnership Firm
- PAN
- AACFO7322D
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/180130/002241 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
None on RERA Karnataka.
Documents
87 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Construction
- ₹80.0 lakh
- Total project cost
- ₹8.5 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station4.95 kmReliable
- Nearest railway station2.18 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km6Caveat
- Nearest lake / water body (≥2 ha)0.94 kmCaveat
Hospitals
- Nearest hospital0.56 kmCaveat
Schools
- Schools in pincode 560035 (UDISE+ census)45Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
- Median pupil-teacher ratio, schools within 1 km18.5 :1Caveat
- Schools with library + playground + ICT lab (1 km)2Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionBellanduru PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km1Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)4.9 kmReliable
- Nearest sewage treatment plant2.29 kmCaveat
- Industrial zones within 1 km1Caveat
- Nearest airfield runway (any, incl. military)6.7 kmCaveat
- Nearest commercial-airport runway32.95 kmReliable
- Distance to runway approach-path proxy32.28 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat
ReliableFrom our location report at the builder-entered pin (12.89163, 77.69368), 2026-10-24. Each figure's source and caveat are in the full report.