The Magic Faraway Tree Phase 2

by Total Environment Building Systems Pvt Ltd · 240 homes · 2.01 acres · 2 towers · Bengaluru South

Upcoming Under construction, due Sep 2027, after an extension. 82% built with 91% of the time used. 93% of homes booked.

Location report

At a glance

Is it on schedule?Deadline extended
82% built

Due 30 Sep 2027. 91% of the time from RERA approval to the deadline has passed.

Built82%
Time used91%
How much is sold?17 left
93% booked

223 of 240 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
119 homes per acre

Similar projects within 3 km: 61 per acre. 61% of the land is left open.

Any complaints?See the list
3 complaints

Complaints to RERA about this project. 11 more about the builder's other projects.

Any legal cases?Litigation
Declared

The builder declares litigation on the land or the project.

What is the builder's record?9 due so far
11% on time

Of its 22 RERA projects in Bengaluru Urban: 1 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 13 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started2 Mar 2016
  2. Approved by RERA15 Oct 2017
  3. First promised31 Dec 2023

    The date the builder gave at registration.

  4. Today24 Oct 2026

    91% of the time to the deadline has passed.

  5. If it slips like a typical project1 Jul 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2697%
Q4 2025-2667%
Q1 2026-2772%
Q2 2026-2782%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower 03 (B2-as per sanction)75%
Tower 04 (B3-as per sanction)90%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

223 booked17 leftQ2 2026-27

Still available: 17 × 3BHK.

Booked, by type

3BHK223 of 240

Booked, each quarter

Q3 2025-26223 of 240
Q4 2025-26223 of 240
Q1 2026-27223 of 240
Q2 2026-27223 of 240

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK
2,562 sq ft
238 m² carpet · sizes 1,647–2,648 sq ft (112 at this size)
53 m² balcony/terrace · 2 parking spaces
240 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower 03 (B2-as per sanction)29 floors
Tower 04 (B3-as per sanction)30 floors

Tower 03 (B2-as per sanction): 120 homes, 2 basements · Tower 04 (B3-as per sanction): 120 homes, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project119
Typical within 3 km (5)61
Typical in the city (114)79

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project61%
Typical within 3 km (5)63%
Typical in the city (118)63%

The share of the land not built on, which includes roads.

Land
2.01 acres

8,149 m²

Ground covered by buildings
39% of the land

3,176 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active mixed development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 22 RERA projects of Total Environment on the map

Complaints to RERA about its other projects

The company

Registered as
Total Environment Building Systems Pvt Ltd
Type
Company
Company number
U45202KA1996PTC020790

CIN or LLPIN, from the Registrar of Companies.

PAN
AABCT9452F

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹10.3 cr
Construction
₹433.6 cr
Total project cost
₹443.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹3.8 cr₹3.8 cr
Q4 2025-26₹6.0 cr₹5.9 cr
Q1 2026-27₹3.4 cr₹3.4 cr
Q2 2026-27₹3.1 cr₹3.1 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.16 kmReliable
  • Nearest railway station8.11 kmReliable
  • Bus stops within 500 m4Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km13Caveat
  • Nearest lake / water body (≥2 ha)0.7 kmCaveat

Hospitals

  • Nearest hospital2.56 kmCaveat

Schools

  • Schools in pincode 560062 (UDISE+ census)66Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
  • Schools with library + playground + ICT lab (1 km)3Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionThalaghattapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km1Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well8.2 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)7.54 kmReliable
  • Nearest sewage treatment plant5.57 kmCaveat
  • Industrial zones within 1 km3Caveat
  • Nearest airfield runway (any, incl. military)16.61 kmCaveat
  • Nearest commercial-airport runway40.32 kmReliable
  • Distance to runway approach-path proxy36.19 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.86031, 77.53036), 2026-10-24. Each figure's source and caveat are in the full report.