Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

The lake Terraces

by KEYA HOMES INFRA LLP · 409 homes · 2.13 acres · 2 towers · Anekal

Delivered on time Completed: the builder filed for completion on 22 Jul 2026, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 22 Jul 2026, by the date it promised.

How much is sold?214 left
48% booked

195 of 409 homes, as the builder reported for Q4 2025-26.

How crowded is it?More crowded
192 homes per acre

Similar projects within 3 km: 83 per acre. 76% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started1 Feb 2024
  2. Approved by RERA17 Aug 2024
  3. Completion filed22 Jul 2026

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

How much is built, each quarter

Q3 2025-2687%
Q4 2025-26100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q4 2025-26

Tower A100%
Tower B100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

195 booked214 leftQ4 2025-26

Still available: 20 × 1 BHK, 185 × 2 BHK, 9 × 3 BHK.

Booked, by type

1 BHK21 of 41
2 BHK137 of 322
3 BHK37 of 46

Booked, each quarter

Q3 2025-26181 of 409
Q4 2025-26195 of 409

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2 BHK
818 sq ft
76 m² carpet · sizes 818–842 sq ft (301 at this size)
21 m² land share · 5 m² balcony/terrace · 1 parking space
322 homes · 79% of the project
3 BHK
1,066 sq ft
99 m² carpet
27 m² land share · 4 m² balcony/terrace · 1 parking space
46 homes · 11% of the project
1 BHK
483 sq ft
45 m² carpet
13 m² land share · 4 m² balcony/terrace · 1 parking space
41 homes · 10% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A22 floors
Tower B24 floors

Tower A: 187 homes, 74 m tall, 3 basements · Tower B: 222 homes, 76 m tall, 3 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project192
Typical within 3 km (39)83
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project76%
Typical within 3 km (39)62%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.13 acres

8,610 m²

Ground covered by buildings
24% of the land

2,042 m²

Floor-area ratio
41321.00

Floors built per unit of land: 41321.00 m² of floors for each m² of land.

Parking
1.12 per home

460 covered, 0 open

Built-up area, all floors
6,75,413 sq ft

62,748 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
KEYA HOMES INFRA LLP
Type
Partnership Firm
Company number
AAQ-4307

CIN or LLPIN, from the Registrar of Companies.

PAN
AAVFK3908N
GSTIN
29AAVFK3908N1ZF
Website
www.keyahomes.in

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹1.8 crBuilding and development ₹144.9 crTotal ₹146.7 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹113.3 cr₹128.1 cr
Q4 2025-26₹113.3 cr₹147.4 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.76 kmReliable
  • Nearest railway station5.4 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km2Caveat
  • Parks within 1 km9Caveat
  • Nearest lake / water body (≥2 ha)0.32 kmCaveat

Hospitals

  • Nearest hospital1.07 kmCaveat

Schools

  • Schools in pincode 560100 (UDISE+ census)75Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
  • Median pupil-teacher ratio, schools within 1 km14.2 :1Caveat
  • Schools with library + playground + ICT lab (1 km)3Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionAttibele PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km3Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)4.08 kmReliable
  • Nearest sewage treatment plant3.47 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)13.19 kmCaveat
  • Nearest commercial-airport runway39.87 kmReliable
  • Distance to runway approach-path proxy38.69 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.82989, 77.66420), 2026-10-24. Each figure's source and caveat are in the full report.