RERA project · Residential/Group Housing
THE GREENS PHASE I
by Sanchaya Land And Estate Pvt Ltd · 1,278 homes · 12.61 acres · 16 towers · Anekal
Past due, no completion filed Past its deadline of 31 Dec 2014, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Dec 2014, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 96 per acre. 77% of the land is left open.
Complaints to RERA about this project. 107 more about the builder's other projects.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started16 Mar 2013
- Deadline31 Dec 2014
Passed with no completion filed.
- Approved by RERA15 Oct 2017
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Amber Tower A: 90 homes, 1 basement · Amber Tower B: 72 homes, 1 basement · Amber Tower C: 72 homes, 1 basement · Amber Tower D: 72 homes, 1 basement · Amber Tower E: 72 homes, 1 basement · Pine Tower A: 72 homes, 1 basement · Pine Tower B: 72 homes, 1 basement · Pine Tower C: 90 homes, 1 basement · Pine Tower D: 90 homes, 1 basement · Pine Tower E: 90 homes, 1 basement · Maple Tower A: 90 homes, 1 basement · Maple Tower B: 90 homes, 1 basement · Maple Tower C: 90 homes, 1 basement · Maple Tower D: 72 homes, 1 basement · Maple Tower E: 72 homes, 1 basement · Teak Block: 72 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 12.61 acres
- Ground covered by buildings
- 23% of the land
51,040 m²
11,826 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of Sanchaya Land And Estate Pvt Ltd on the map
Complaints to RERA about its other projects
- skyview 69 complaints
- THE GREENS PHASE II 36 complaints
- SKYVIEW 1 complaint
- skyview:::PRM/KA/RERA/1250/303/PR/170905/000071 1 complaint
The company
- Registered as
- Sanchaya Land And Estate Pvt Ltd
- Type
- Company
- Company number
- U70100KA2012PTC061973
- PAN
- AAQCS8180A
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/171015/000701 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Complaint under Section 31 RERA Act r/w Rule 29 and 30 Karnataka RERA Rules for Refund of Invested Amount 27 Feb 2019 · Disposed Authority Fullbench
- NON DELIVERY OF APARTMENT, NON PAYMENT OF PRE-EMI, DELAYED COMPENSATION,INTEREST REFUND, DAMAGE FOR MENTAL AGONY AND UNFAIR TRADE PRACTICES 28 Jul 2019 · Disposed Ao
- Invalid cancellation notice from builder, Need refund 7 Aug 2019 · Disposed Ao
- Delay in completion of project 16 Aug 2019 · Disposed Ao
- Cheated by Indya Estates - 5 Years of ordeal continues 10 Sep 2019 · Disposed Authority Bench5
- Cheated by Indya Estates, Sanchaya Land & Estates - 5 Years of ordeal continues 22 Sep 2019 · Disposed Ao
- ACTION FOR VIOLATION OF SECTION 3 & 4, INITIATE FORENSIC AUDIT, CANCELLATION OF REGISTRATION U/S 6, 7 AND PROCEEDING U/S 8 FOR COMPLETION OF PROJECT AND PENALTIES UNDER VARIOUS PROVISION OF RERA ACT A 30 Oct 2019 · Disposed Authority Fullbench
- Refund of money with interest and delay compensation 4 Feb 2020 · Disposed Ao
- Cancellation of agreement & refund for non completion of project 15 Feb 2020 · Disposed Authority Bench5
- Agreement Cancellation and refund for non completion of project 18 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 23 Feb 2020 · Disposed Authority Bench5
- Claim for Compensation under Section 31 with Section 71 of the Act 23 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under sec 31 with section 71 of the Act 24 Feb 2020 · Disposed Authority Bench5
- Claim for Compensation and Others 24 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 24 Feb 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 with section 71 of the RERA Act 24 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under sec 31 with section 71 of the act 24 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 and section 71 of the Act 24 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 and section 71 of the Act 24 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 read with section 71 of the Act 25 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the act 25 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 25 Feb 2020 · Disposed Authority Bench6
- Claim for compensation under sec 31 with sec 71 of the Act 25 Feb 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 with section 71 of the Act 25 Feb 2020 · Disposed Authority Bench5
- CLAIM FOR COMPENSATION UNDER SECTION 31 WITH SECTION 71 OF THE ACT 25 Feb 2020 · Disposed Authority Fullbench
- Claim for compensation under section 31 read with section 71 of the Act 25 Feb 2020 · Disposed Authority Fullbench
- Claim for compensation under section 31 read with section 71 of the Act 25 Feb 2020 · Disposed Authority Bench5
- Claim for Compensation under Section 31 with Section 71 of the Act 26 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31with section 71 of the act 26 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 27 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the acr 28 Feb 2020 · Disposed Authority Bench5
- Delay Compensation & Possession with OC,KHATA,AMENITIES 28 Feb 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 read with section 71 of the Act 28 Feb 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 2 Mar 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 read with section 71 of the Act 9 Mar 2020 · Disposed Authority Bench6
- Delay in handing over the unit 14 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under Section 31 with Section 71 of the Act 14 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under Section 31 with section 71 of the Act 14 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 read with section 71 of the Act 16 Mar 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 read with section 71 of the Act 17 Mar 2020 · Disposed Authority Bench5
- Delay in completion of the project and legal possession 19 Mar 2020 · Disposed Authority Bench6
- Delivery with Delay Compensation 19 Mar 2020 · Disposed Authority Bench5
- Project incomplete, Pre-EMI not reimburse, Delayed compensation, Unfair trade practices, illegal cancellation note or demand note, etc. 20 Mar 2020 · Disposed Authority Bench5
- Claim for compensation for delayed delivery of the apartment with necessary documents 20 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 read with section 71 of the Act 20 Mar 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 read with section 71 of the Act 21 Mar 2020 · Disposed Authority Bench6
- Claim for compensation under section 31 read with section 71 of the Act 21 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 read with section 71 of the Act 21 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 read with section 71 of the Act 21 Mar 2020 · Disposed Authority Bench6
- Refund of amout paid with interest as compensation 21 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under Section 31 with section 71 of the Act 21 Mar 2020 · Disposed Authority Bench6
- CLAIM FOR COMPENSATION UNDER SECTION 31 READ WITH SECTION 71 OF THE ACT 24 Mar 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 17 Apr 2020 · Disposed Authority Bench5
- Claim for compensation under Section 31 with Section 71 of the Act 15 May 2020 · Disposed Authority Fullbench
- FAILURE TO DELIVER FLAT SINCE JUNE 2015 24 Jun 2020 · Disposed Authority Bench5
- Swindling of Rs. 10,26,500/- (Ten Lac Twenty Six Thousand Fivr Hundred Only) by Rohit Lomesh (Director), Pankaj Kalra (Manager) employees of SANCHALAYA LAND & ESTATES PVT. LTD., (Indya Estates Delhi 11 Aug 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 with section 71 of the Act 29 Aug 2020 · Disposed Authority Bench5
- Claim for compensation under Section 31 with Section 71 of the Act 13 Oct 2020 · Disposed Authority Bench5
- Claim for compensation under section 31 read with section 71 of the Act 4 Nov 2020 · Disposed Authority Bench5
- Breach of Agreement & delay in delivery 1 Dec 2020 · Disposed Authority Fullbench
- Delay In Possession and Breach of Contract by builder 6 Mar 2021 · Disposed Authority Fullbench
- Failure to register Flat No. 105, 1st Floor, Maple Block, 'B' Tower in "The Greens" by Indya Estates Group/Sanchaya Land and Estate Pvt. Ltd to Complainant 9 Jun 2021 · Disposed Authority Fullbench
- Project delayed, bad construction quality, non-availability of power and water supply 2 Aug 2021 · Disposed Authority Fullbench
- Project Not Delivered on time 2 Aug 2021 · Disposed Authority Fullbench
- REFUND AND COMPENSATION FOR DELAY IN PROJECT 10 Nov 2021 · Disposed Authority Bench4
- Cancellation of the fraudulent sale agreement and refund of the Rs.59,15,391/- with 24% interest P.A compensation of Rs.1 Crore for causing great hardship and mental agony to the Complainant . 26 Nov 2021 · Disposed Authority Bench5
- Refund of 2L INR against cancellation of Maple 504 14 Dec 2021 · Disposed Authority Fullbench
- FLAT NO MAPLE C 809 STILL NOT HANDED OVER AND NON PAYEMENT OF PRE EMI WITH INTEREST 15 Dec 2021 · Disposed Authority Fullbench
- Refund with interest as the project is not completed even after nine years after paying full amount. 16 May 2022 · Disposed Authority Fullbench
- Failure to update status on flat's possession, completion and compensation 24 May 2022 · Disposed Authority Fullbench
- Non payment of Compensation 7 Sep 2022 · Disposed Authority Fullbench
- Refund of the entire amount paid for the property with interest till date. 7 Nov 2022 · Disposed Authority Fullbench
- Refund of the entire amount paid for the property and the interest for the same till date. 7 Nov 2022 · Disposed Authority Fullbench
- Refund of the Entire amount paid for the property and the interest for the same till date. 10 Nov 2022 · Disposed Authority Fullbench
- Refund of the amounts paid with up-to-date interest and penalty 21 Dec 2022 · Disposed Authority Fullbench
- DELAYED INTEREST, POSSESSION OF APARTMENT AND PROJECT COMPLETION 17 Jan 2023 · Disposed Authority Fullbench
- DELAYED INTEREST, POSSESSION OF APARTMENT AND PROJECT COMPLETION 17 Jan 2023 · Disposed Authority Fullbench
- DELAYED INTEREST, POSSESSION OF APARTMENT AND PROJECT COMPLETION 17 Jan 2023 · Disposed Authority Fullbench
- DELAYED INTEREST, POSSESSION OF APARTMENT AND PROJECT COMPLETION 17 Jan 2023 · Disposed Authority Fullbench
- Bouncing of Refund Cheque 7 Feb 2023 · Disposed Authority Fullbench
- Seeking bribe....Refusal to register for not paying cash without receipt 29 Mar 2023 · Disposed Authority Fullbench
- Refund of the Entire Amount Paid for the Property and Interest for the same till date. 30 Mar 2023 · Disposed Authority Fullbench
- Refund of the Entire Amount Paid for the Property and Interest for the same till Date 11 Apr 2023 · Disposed Authority Fullbench
- Refund of the entire amount paid for the said property and Interest for the same till date 18 Apr 2023 · Disposed Authority Bench4
- Refund of the entire amount paid with interest till date. 18 Apr 2023 · Disposed Authority Fullbench
- FILING OF SUIT AGAINST BUILDER FOR RETURN OF FUND WITH COMPENSATION 20 May 2023 · Disposed Authority Fullbench
- Refund 1 Dec 2023 · Disposed Authority Fullbench
- Compensation 14 Dec 2023 · Disposed Ao
- Pending Amenities, Possession Delivery, Completion of Project in all respect to make it Habitable. 4 Jul 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 14 Jul 2025 · Disposed Authority Bench4
- Delay in handing over possession 30 Jul 2025 · Disposed Authority Bench4
- Delay in completion of project, Non delivery of Habitual Possession of Flat, No Occupancy Certificate, Pay Interest for Delay 22 Sep 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 25 Sep 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 25 Sep 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 25 Sep 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 13 Oct 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 13 Oct 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 13 Oct 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 13 Oct 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 16 Oct 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 3 Nov 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 3 Nov 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 3 Nov 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 3 Nov 2025 · Disposed Authority Bench4
- Pending Amenities, Possession Delivery, Completion of Project in all respect to make it Habitable. 4 Nov 2025 · Disposed Authority Bench4
- Pending Amenities, Possession Delivery, Completion of Project in all respect to make it Habitable 4 Nov 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 4 Nov 2025 · Disposed Authority Bench4
- Interest of Delay Period, Deliver of Habitual Possession of Flat with OC and Permanent Electricity, Water and Amenieies as agreed under Agreement 14 Nov 2025 · Disposed Authority Bench4
- breach of agreement 29 May 2026 · Disposed Authority Bench4
Documents
51 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹10.7 cr
- Construction
- ₹181.0 cr
- Total project cost
- ₹248.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.