RERA project · Residential/Group Housing
SUMADHURA PRAMODA
by SUMADHURA INFRACON PRIVATE LIMITED · 297 homes · 3.45 acres · 2 towers · Bengaluru South
Upcoming Under construction, due Dec 2029. 55% built with 33% of the time used. 50% of homes booked.
At a glance
Due 31 Dec 2029. 33% of the time from RERA approval to the deadline has passed.
148 of 297 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 81 per acre. 82% of the land is left open.
Complaints to RERA about this project. 4 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 27 RERA projects in Bengaluru Urban: 2 delivered on time, 10 late (after the date first promised), 15 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started17 Mar 2025
- Approved by RERA25 Mar 2025
- Today24 Oct 2026
33% of the time to the deadline has passed.
- Deadline31 Dec 2029
The date it must be complete by.
- If it slips like a typical project2 Oct 2030
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 33 × 2 BHK Luxe, 45 × 3 BHK Luxe, 1 × 1 BHK, 70 × 3 BHK Smart.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Block-A: 135 homes, 90 m tall, 3 basements · Block-B: 162 homes, 90 m tall, 3 basements
Amenities
- Electricity 254 m²
- Smart Home Automation 12,936 m²
- CCTV Surveillance 13,959 m²
- Club House 2,176 m²
- Community Hall 259 m²
- Outdoor Sports facility 1,400 m²
- Indoor Sports facility 265 m²
- Swimming Pool 471 m²
- Gym 178 m²
- Parks 1,474 m²
- Power Backup 121 m²
- Water and Sanitation 471 m²
- Air Conditioning 2,176 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.45 acres
- Ground covered by buildings
- 18% of the land
- Floor-area ratio
- 3.25
- Parking
- 1.15 per home
- Built-up area, all floors
- 6,97,382 sq ft
13,962 m²
2,481 m²
Floors built per unit of land: 3.25 m² of floors for each m² of land.
328 covered, 13 open
64,789 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 27 RERA projects of Sumadhura on the map
Complaints to RERA about its other projects
- SUMADHURA NANDANAM 1 complaint
- FOLIUM BY SUMADHURA PHASE-I 1 complaint
- FOLIUM BY SUMADHURA PHASE-II 1 complaint
- SUMADHURA EDITION PHASE-I 1 complaint
The company
- Registered as
- SUMADHURA INFRACON PRIVATE LIMITED
- Type
- Company
- Company number
- U45200KA2012PTC062071
- PAN
- AAQCS9641A
- GSTIN
- 29AAQCS9641A1ZZ
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
20 registrations under this company
- Sumadhura Belfort PRM/KA/RERA/1250/304/PR/230926/008960 · approved 23 Sep 2026
- FOLIUM BY SUMADHURA PHASE-IV PRM/KA/RERA/1251/446/PR/050126/008382 · approved 5 Jan 2026
- SUMADHURA SOLACE PHASE-II PRM/KA/RERA/1251/446/PR/111225/008333 · approved 11 Dec 2025
- SUMADHURA EDITION PHASE-II PRM/KA/RERA/1251/446/PR/111225/008332 · approved 11 Dec 2025
- SUMADHURA SOLACE PHASE-I PRM/KA/RERA/1251/446/PR/111225/008330 · approved 11 Dec 2025
- SUMADHURA EDITION PHASE-I PRM/KA/RERA/1251/446/PR/111225/008328 · approved 11 Dec 2025
- SARANG BY SUMADHURA PHASE-II PRM/KA/RERA/1251/446/PR/050225/007481 · approved 5 Feb 2025
- SUMADHURA CAPITOL RESIDENCES PRM/KA/RERA/1251/446/PR/051024/007125 · approved 5 Oct 2024
- SUMADHURA THRIVE PRM/KA/RERA/1251/446/PR/051024/007124 · approved 5 Oct 2024
- HIVE BY SUMADHURA PRM/KA/RERA/1251/446/PR/051024/007123 · approved 5 Oct 2024
- FOLIUM BY SUMADHURA PHASE-III PRM/KA/RERA/1251/446/PR/141223/006468 · approved 14 Dec 2023
- SARANG BY SUMADHURA PHASE-I PRM/KA/RERA/1251/446/PR/180723/006075 · approved 18 Jul 2023
- FOLIUM BY SUMADHURA PHASE-II PRM/KA/RERA/1251/446/PR/250423/005893 · approved 25 Apr 2023
- FOLIUM BY SUMADHURA PHASE-I PRM/KA/RERA/1251/446/PR/280222/004738 · approved 28 Feb 2022
- SUMADHURA SUSHANTHAM PHASE II PRM/KA/RERA/1251/309/PR/200205/003253 · approved 5 Feb 2020
- SUMADHURA SUSHANTHAM PHASE I PRM/KA/RERA/1251/309/PR/200103/003118 · approved 3 Jan 2020
- SUMADHURA SOHAM PHASE II PRM/KA/RERA/1251/446/PR/190423/002529 · approved 23 Apr 2019
- SUMADHURA NANDANAM PRM/KA/RERA/1251/446/PR/180507/001667 · approved 7 May 2018
- SUMADHURA EDEN GARDEN PRM/KA/RERA/1251/446/PR/180328/002632 · approved 28 Mar 2018
- SUMADHURA SOHAM PHASE-I PRM/KA/RERA/1251/446/PR/171123/000704 · approved 23 Nov 2017
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/250325/007625 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · PRJ/7335/24-25 · 17 Mar 2025
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBWSSB,Local Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
142 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹20.0 cr | ₹12.5 cr |
| Q4 2025-26 | ₹30.3 cr | ₹21.0 cr |
| Q1 2026-27 | ₹18.3 cr | ₹13.7 cr |
| Q2 2026-27 | ₹19.0 cr | ₹13.1 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station0.98 kmReliable
- Nearest railway station2.14 kmReliable
- Bus stops within 500 m3Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km7Caveat
- Nearest lake / water body (≥2 ha)0.79 kmCaveat
Hospitals
- Nearest hospital0.75 kmCaveat
Schools
- Schools in pincode 560059 (UDISE+ census)12Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
- Schools with library + playground + ICT lab (1 km)2Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionKengeri PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)11 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km5Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)14.66 kmReliable
- Nearest sewage treatment plant1.73 kmCaveat
- Industrial zones within 1 km6Caveat
- Nearest airfield runway (any, incl. military)16.22 kmCaveat
- Nearest commercial-airport runway35.05 kmReliable
- Distance to runway approach-path proxy29.87 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.92905, 77.50593), 2026-10-24. Each figure's source and caveat are in the full report.