RERA project · Residential/Group Housing

SUMADHURA EDITION PHASE-II

by SUMADHURA INFRACON PRIVATE LIMITED · 450 homes · 4.77 acres · 3 towers · Bengaluru East

Upcoming Under construction, due Dec 2029. 28% built with 21% of the time used. 24% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
28% built

Due 31 Dec 2029. 21% of the time from RERA approval to the deadline has passed.

Built28%
Time used21%
How much is sold?341 left
24% booked

109 of 450 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
94 homes per acre

Similar projects within 3 km: 73 per acre. 87% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 4 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?12 due so far
17% on time

Of its 27 RERA projects in Bengaluru Urban: 2 delivered on time, 10 late (after the date first promised), 15 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Nov 2025
  2. Approved by RERA11 Dec 2025
  3. Today24 Oct 2026

    21% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2030

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2627%
Q4 2025-2621%
Q1 2026-2721%
Q2 2026-2728%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

(Wing - I) Orion11%
(Wing - J) Tucana10%
(Wing - K) Vela9%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

109 booked341 leftQ2 2026-27

Still available: 83 × Classic 3bhk, 43 × Classic 2 bhk, 84 × Grand 3bhk, 40 × Grand 4 bhk, 56 × Smart 3 bhk, 35 × Smart 4 bhk.

Booked, by type

Classic 3bhk25 of 108
Classic 2 bhk14 of 57
Grand 3bhk30 of 114
Grand 4 bhk17 of 57
Smart 3 bhk1 of 57
Smart 4 bhk22 of 57

Booked, each quarter

Q3 2025-260 of 450
Q4 2025-2689 of 450
Q1 2026-27105 of 450
Q2 2026-27109 of 450

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

Grand 3bhk
1,159 sq ft
108 m² carpet
43 m² land share · 20 m² balcony/terrace · 1 parking space
114 homes · 25% of the project
Classic 3bhk
1,094 sq ft
102 m² carpet · sizes 957–1,094 sq ft (57 at this size)
40 m² land share · 19 m² balcony/terrace · 1 parking space
108 homes · 24% of the project
Smart 3 bhk
954 sq ft
89 m² carpet
36 m² land share · 17 m² balcony/terrace · 1 parking space
57 homes · 13% of the project
Classic 2 bhk
826 sq ft
77 m² carpet
32 m² land share · 18 m² balcony/terrace · 1 parking space
57 homes · 13% of the project
Grand 4 bhk
1,464 sq ft
136 m² carpet
53 m² land share · 21 m² balcony/terrace · 1 parking space
57 homes · 13% of the project
Smart 4 bhk
1,245 sq ft
116 m² carpet
46 m² land share · 20 m² balcony/terrace · 1 parking space
57 homes · 13% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

(Wing - I) Orion18 floors
(Wing - J) Tucana18 floors
(Wing - K) Vela18 floors

(Wing - I) Orion: 150 homes, 57 m tall, 2 basements · (Wing - J) Tucana: 150 homes, 57 m tall, 2 basements · (Wing - K) Vela: 150 homes, 57 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project94
Typical within 3 km (89)73
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project87%
Typical within 3 km (89)63%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.77 acres

19,291 m²

Ground covered by buildings
13% of the land

2,462 m²

Floor-area ratio
2.24

Floors built per unit of land: 2.24 m² of floors for each m² of land.

Parking
1.63 per home

735 covered, 0 open

Built-up area, all floors
10,40,385 sq ft

96,655 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 27 RERA projects of Sumadhura on the map

Complaints to RERA about its other projects

The company

Registered as
SUMADHURA INFRACON PRIVATE LIMITED
Type
Company
Company number
U45200KA2012PTC062071

CIN or LLPIN, from the Registrar of Companies.

PAN
AAQCS9641A
GSTIN
29AAQCS9641A1ZZ

Its other registrations on RERA Karnataka

20 registrations under this company
  • Sumadhura Belfort PRM/KA/RERA/1250/304/PR/230926/008960 · approved 23 Sep 2026
  • FOLIUM BY SUMADHURA PHASE-IV PRM/KA/RERA/1251/446/PR/050126/008382 · approved 5 Jan 2026
  • SUMADHURA SOLACE PHASE-II PRM/KA/RERA/1251/446/PR/111225/008333 · approved 11 Dec 2025
  • SUMADHURA SOLACE PHASE-I PRM/KA/RERA/1251/446/PR/111225/008330 · approved 11 Dec 2025
  • SUMADHURA EDITION PHASE-I PRM/KA/RERA/1251/446/PR/111225/008328 · approved 11 Dec 2025
  • SUMADHURA PRAMODA PRM/KA/RERA/1251/310/PR/250325/007625 · approved 25 Mar 2025
  • SARANG BY SUMADHURA PHASE-II PRM/KA/RERA/1251/446/PR/050225/007481 · approved 5 Feb 2025
  • SUMADHURA CAPITOL RESIDENCES PRM/KA/RERA/1251/446/PR/051024/007125 · approved 5 Oct 2024
  • SUMADHURA THRIVE PRM/KA/RERA/1251/446/PR/051024/007124 · approved 5 Oct 2024
  • HIVE BY SUMADHURA PRM/KA/RERA/1251/446/PR/051024/007123 · approved 5 Oct 2024
  • FOLIUM BY SUMADHURA PHASE-III PRM/KA/RERA/1251/446/PR/141223/006468 · approved 14 Dec 2023
  • SARANG BY SUMADHURA PHASE-I PRM/KA/RERA/1251/446/PR/180723/006075 · approved 18 Jul 2023
  • FOLIUM BY SUMADHURA PHASE-II PRM/KA/RERA/1251/446/PR/250423/005893 · approved 25 Apr 2023
  • FOLIUM BY SUMADHURA PHASE-I PRM/KA/RERA/1251/446/PR/280222/004738 · approved 28 Feb 2022
  • SUMADHURA SUSHANTHAM PHASE II PRM/KA/RERA/1251/309/PR/200205/003253 · approved 5 Feb 2020
  • SUMADHURA SUSHANTHAM PHASE I PRM/KA/RERA/1251/309/PR/200103/003118 · approved 3 Jan 2020
  • SUMADHURA SOHAM PHASE II PRM/KA/RERA/1251/446/PR/190423/002529 · approved 23 Apr 2019
  • SUMADHURA NANDANAM PRM/KA/RERA/1251/446/PR/180507/001667 · approved 7 May 2018
  • SUMADHURA EDEN GARDEN PRM/KA/RERA/1251/446/PR/180328/002632 · approved 28 Mar 2018
  • SUMADHURA SOHAM PHASE-I PRM/KA/RERA/1251/446/PR/171123/000704 · approved 23 Nov 2017

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹109.2 crBuilding and development ₹493.6 crTotal ₹602.8 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹0.0 lakh₹0.0 lakh
Q4 2025-26₹31.3 cr₹20.7 cr
Q1 2026-27₹45.7 cr₹31.3 cr
Q2 2026-27₹27.3 cr₹17.9 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.88 kmReliable
  • Nearest railway station5.28 kmReliable
  • Bus stops within 500 m1Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km10Caveat
  • Nearest lake / water body (≥2 ha)0.54 kmCaveat

Hospitals

  • Nearest hospital0.45 kmCaveat

Schools

  • Schools in pincode 560066 (UDISE+ census)44Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
  • Schools with library + playground + ICT lab (1 km)3Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionWhitefield PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km1Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)11.31 kmReliable
  • Nearest sewage treatment plant1.65 kmCaveat
  • Industrial zones within 1 km8Caveat
  • Nearest airfield runway (any, incl. military)5.01 kmCaveat
  • Nearest commercial-airport runway25.33 kmReliable
  • Distance to runway approach-path proxy24.57 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.96028, 77.72962), 2026-10-24. Each figure's source and caveat are in the full report.