SUMADHURA EDEN GARDEN

by SUMADHURA INFRACON PRIVATE LIMITED · 724 homes · 13.87 acres · 12 towers · Bengaluru East

Delivered late Completed: the builder filed for completion on 30 Sep 2022, 273 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 30 Sep 2022, 273 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
52 homes per acre

Similar projects within 3 km: 80 per acre. 80% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 4 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?12 due so far
17% on time

Of its 27 RERA projects in Bengaluru Urban: 2 delivered on time, 10 late (after the date first promised), 15 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started29 Dec 2017
  2. Approved by RERA28 Mar 2018
  3. First promised31 Dec 2021

    The date the builder gave at registration.

  4. Completion filed30 Sep 2022

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2 BHK
766 sq ft
71 m² carpet · sizes 766–843 sq ft (116 at this size)
40 m² land share · 18 m² balcony/terrace · 1 parking space
343 homes · 47% of the project
3 BHK
1,065 sq ft
99 m² carpet · sizes 1,065–1,086 sq ft (73 at this size)
54 m² land share · 24 m² balcony/terrace · 1 parking space
145 homes · 20% of the project
2.5 BHK
982 sq ft
91 m² carpet · sizes 962–982 sq ft (121 at this size)
50 m² land share · 22 m² balcony/terrace · 1 parking space
142 homes · 20% of the project
1 BHK
435 sq ft
40 m² carpet
24 m² land share · 11 m² balcony/terrace · 1 parking space
94 homes · 13% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Wing A14 floors
Wing B14 floors
Wing C14 floors
Wing D14 floors
Wing E14 floors
Wing F14 floors
Wing G14 floors
Wing H14 floors
Wing I14 floors
Wing J14 floors
Wing K14 floors
Wing L14 floors

Wing A: 61 homes, 1 basement · Wing B: 67 homes, 1 basement · Wing C: 57 homes, 1 basement · Wing D: 59 homes, 1 basement · Wing E: 44 homes, 1 basement · Wing F: 44 homes, 1 basement · Wing G: 54 homes, 1 basement · Wing H: 74 homes, 2 basements · Wing I: 63 homes, 2 basements · Wing J: 45 homes, 2 basements · Wing K: 94 homes, 2 basements · Wing L: 62 homes, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project52
Typical within 3 km (92)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project80%
Typical within 3 km (91)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
13.87 acres

56,114 m²

Ground covered by buildings
14% of the land

8,007 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 27 RERA projects of Sumadhura on the map

Complaints to RERA about its other projects

The company

Registered as
SUMADHURA INFRACON PRIVATE LIMITED
Type
Company
Company number
U45200KA2012PTC062071

CIN or LLPIN, from the Registrar of Companies.

PAN
AAQCS9641A

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Construction
₹376.6 cr
Total project cost
₹376.6 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station3.12 kmReliable
  • Nearest railway station3.16 kmReliable
  • Bus stops within 500 m1Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km5Caveat
  • Nearest lake / water body (≥2 ha)0.49 kmCaveat

Hospitals

  • Nearest hospital1.24 kmCaveat

Schools

  • Schools in pincode 560067 (UDISE+ census)57Caveat
  • Median pupil-teacher ratio, schools within 1 km24.1 :1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKadugodi PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well60.8 m below groundCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.89 kmReliable
  • Nearest sewage treatment plant1.6 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)6.71 kmCaveat
  • Nearest commercial-airport runway18.56 kmReliable
  • Distance to runway approach-path proxy17.35 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.02326, 77.75155), 2026-10-24. Each figure's source and caveat are in the full report.