Upcoming Under construction, due Dec 2026, after an extension. 90% built with 97% of the time used. 66% of homes booked.

Location report

At a glance

Is it on schedule?Deadline extended
90% built

Due 31 Dec 2026. 97% of the time from RERA approval to the deadline has passed.

Built90%
Time used97%
How much is sold?60 left
66% booked

115 of 175 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
58 homes per acre

Similar projects within 3 km: 96 per acre. 63% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Feb 2021
  2. Approved by RERA4 Aug 2021
  3. First promised31 Aug 2024

    The date the builder gave at registration.

  4. Today24 Oct 2026

    97% of the time to the deadline has passed.

  5. If it slips like a typical project2 Oct 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2675%
Q4 2025-2680%
Q1 2026-2785%
Q2 2026-2790%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block A90%
Block B90%
Block C90%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

115 booked60 leftQ2 2026-27

Still available: 2 × 1BHK, 46 × 2BHK, 12 × 3BHK.

Booked, by type

1BHK8 of 10
2BHK74 of 120
3BHK33 of 45

Booked, each quarter

Q3 2025-26103 of 175
Q4 2025-26109 of 175
Q1 2026-27110 of 175
Q2 2026-27115 of 175

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2BHK
809 sq ft
75 m² carpet · sizes 809–982 sq ft (25 at this size)
66 m² land share
60 homes · 75% of the project
1BHK
434 sq ft
40 m² carpet · sizes 434–526 sq ft (5 at this size)
40 m² land share
10 homes · 12% of the project
3BHK
999 sq ft
93 m² carpet · sizes 999–1,469 sq ft (5 at this size)
98 m² land share
10 homes · 12% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block A4 floors
Block B4 floors
Block C4 floors

Block A: 70 homes, 1 basement · Block B: 10 homes, 1 basement · Block C: 95 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project58
Typical within 3 km (16)96
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project63%
Typical within 3 km (16)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.02 acres

12,241 m²

Ground covered by buildings
37% of the land

4,493 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
SUBRAM BUILDERS
Type
Proprietorship Firm

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹1.9 cr
Construction
₹45.0 cr
Total project cost
₹46.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹7.8 cr₹5.3 cr
Q4 2025-26₹7.3 cr₹4.6 cr
Q1 2026-27₹3.8 cr₹3.5 cr
Q2 2026-27₹8.2 cr₹5.8 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.07 kmReliable
  • Nearest railway station4.01 kmReliable
  • Bus stops within 500 m4Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km5Caveat
  • Nearest lake / water body (≥2 ha)0.38 kmCaveat

Hospitals

  • Nearest hospital1.25 kmCaveat

Schools

  • Schools in pincode 560073 (UDISE+ census)99Caveat
  • Median pupil-teacher ratio, schools within 1 km29.2 :1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionPeenya PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km4Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)10.22 kmReliable
  • Nearest sewage treatment plant0.23 kmCaveat
  • Industrial zones within 1 km5Caveat
  • Nearest airfield runway (any, incl. military)11.79 kmCaveat
  • Nearest commercial-airport runway26.95 kmReliable
  • Distance to runway approach-path proxy20.09 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.04043, 77.49355), 2026-10-24. Each figure's source and caveat are in the full report.