Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

SRI BALAJI SIGNATURE

by SRI BALAJI STRUCTURES · 160 homes · 1.76 acres · 1 tower · Bengaluru East

Past due, no completion filed Past its deadline of 30 Jun 2024, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 30 Jun 2024, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
91 homes per acre

Similar projects within 3 km: 74 per acre. 50% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?1 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started13 Dec 2021
  2. Approved by RERA26 May 2022
  3. Deadline30 Jun 2024

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2 BHK
848 sq ft
79 m² carpet · sizes 823–1,124 sq ft (12 at this size)
40 m² land share · 11 m² balcony/terrace
89 homes · 56% of the project
3 BHK
1,080 sq ft
100 m² carpet · sizes 1,014–1,181 sq ft (12 at this size)
49 m² land share · 13 m² balcony/terrace
71 homes · 44% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Sri Balaji Signature4 floors

Sri Balaji Signature: 160 homes, 14 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project91
Typical within 3 km (69)74
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project50%
Typical within 3 km (70)55%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.76 acres

7,132 m²

Ground covered by buildings
50% of the land

3,566 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
0.00 per home

0 covered, 0 open

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of SRI BALAJI STRUCTURES on the map

The company

Registered as
SRI BALAJI STRUCTURES
Type
Partnership Firm
PAN
AENFS5280H
GSTIN
29AENFS5280H1ZF

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹2.0 crBuilding and development ₹42.1 crTotal ₹44.1 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station7.01 kmReliable
  • Nearest railway station5.23 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km1Caveat
  • Nearest lake / water body (≥2 ha)2.29 kmCaveat

Hospitals

  • Nearest hospital0.61 kmCaveat

Schools

  • Schools in pincode 560077 (UDISE+ census)123Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km23Caveat
  • Median pupil-teacher ratio, schools within 1 km22.1 :1Caveat
  • Schools with library + playground + ICT lab (1 km)11Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionHennur PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)32 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km1Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)5.68 kmReliable
  • Nearest sewage treatment plant1.35 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)4.75 kmCaveat
  • Nearest commercial-airport runway16.24 kmReliable
  • Distance to runway approach-path proxy13.92 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)2Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat

ReliableFrom our location report at the builder-entered pin (13.05235, 77.63685), 2026-10-24. Each figure's source and caveat are in the full report.