Delivered late Completed: the builder filed for completion on 10 Dec 2025, 71 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 10 Dec 2025, 71 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?About the same
14 plots per acre

Similar projects within 3 km: 14 per acre. 45% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised).

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started1 Jul 2024
  2. Approved by RERA27 Sep 2024
  3. Completion filed10 Dec 2025

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

This project's RERA page has no flat-by-flat list, so these are the builder's summary figures, exactly as filed. Builders often give the area of all plots of a size together there: a figure marked "in all" covers every one of them, not one plot.

9.14 m x 15.24 m
38,987 sq ft in all
3,622.0 m² area for all 26 plots together, as filed
26 plots · 60% of the project
ODD
31,969 sq ft in all
2,970.0 m² area for all 17 plots together, as filed
17 plots · 40% of the project

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Plots per acre

This project14
Typical within 3 km (13)14
Typical in the city (593)16

Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project45%
Typical within 3 km (15)49%
Typical in the city (730)46%

The share of the land not built on, which includes roads.

Land
2.97 acres

12,039 m²

Plot area (the sites)
55% of the land

6,592 m²

Roads
3,025 m²
Parks and open spaces
1,215 m²
Civic amenity sites
603 m²

Sites kept for public uses such as a school or a health centre.

CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of Rose lantern Realty Pvt ltd on the map

Complaints to RERA about its other projects

The company

Registered as
Rose Lantern Realty Pvt Ltd
Type
Company
Company number
U70100KA2021PTC148350

CIN or LLPIN, from the Registrar of Companies.

PAN
AALCR0570L
GSTIN
29AALCR0570L1ZW

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development), including Rose Lantern Realty Pvt Ltd Rep by Vijay Krishna Yadav.

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹3.9 crBuilding and development ₹2.5 crTotal ₹6.4 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station15.42 kmReliable
  • Nearest railway station13.29 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.4 kmCaveat

Hospitals

  • Nearest hospital3.59 kmCaveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSarjapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)19.17 kmReliable
  • Nearest sewage treatment plant8.96 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)14.42 kmCaveat
  • Nearest commercial-airport runway37.31 kmReliable
  • Distance to runway approach-path proxy34.35 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.86520, 77.82264), 2026-10-24. Each figure's source and caveat are in the full report.