RERA project · Residential/Group Housing
Sound of Water Phase 2
by Puravankara Limited · 53 homes · 2.29 acres · 1 tower · Bengaluru South
Past due, no completion filed Past its deadline of 30 Jun 2026, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Jun 2026, and no completion is filed.
47 of 53 homes, as the builder reported for Q4 2025-26.
Similar projects across the city: 76 per acre. 25% of the land is left open.
Complaints to RERA about this project. 111 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 37 RERA projects in Bengaluru Urban: 2 delivered on time, 8 late (after the date first promised), 8 past due with no completion filed, 17 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started30 Jun 2021
- Approved by RERA7 Sep 2021
- Deadline30 Jun 2026
Passed with no completion filed.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 5 × 3BHK, 1 × 4BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 1,879 sq ft29 homes174.6 m²
- 2,266 sq ft11 homes210.5 m²
- 2,587 sq ft6 homes240.3 m²
- 2,689 sq ft1 home249.8 m²
- 103 sq ft6 homes9.6 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Sow 2: 53 homes
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 2.29 acres
- Ground covered by buildings
- 75% of the land
9,279 m²
6,988 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 37 RERA projects of Puravankara on the map
Complaints to RERA about its other projects
111 complaints across 18 projects. The most complained about:
- Provident Park Square Phase - 1 18 complaints
- Provident Park Square 4 16 complaints
- Purva Palmbeach 14 complaints
- Purva Park Hill (Wing D) 13 complaints
- Provident Park Square Phase 3 (Towers 5A and 5B) 8 complaints
Show all 18 projects
- Purva Park Hill (Wing C) 7 complaints
- Purva Sunflower 6 complaints
- Purva Westend Phase 1 5 complaints
- Provident Woodfield 5 complaints
- Purva Atmosphere 5 complaints
- Provident Park Square Phase 2 3 complaints
- Purva Oakshire 3 complaints
- Provident Park Square 5 2 complaints
- Sound of Water Phase 1 by Puravankara 2 complaints
- PURVA PALMBEACH 1 complaint
- Purva Coronation Square 1 complaint
- Purva Zenium 2 1 complaint
- Purva Zenium 1 1 complaint
The company
- Registered as
- Puravankara Limited
- Type
- Company
- PAN
- AAACP2550R
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/210907/004300 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q4 2025-26 update
Complaints to RERA about this project
None on RERA Karnataka.
Documents
110 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹24.9 cr
- Construction
- ₹64.2 cr
- Total project cost
- ₹89.1 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹9.1 cr | ₹6.7 cr |
| Q4 2025-26 | ₹7.9 cr | ₹5.6 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.