RERA project · Residential/Group Housing
SNR Verity
by SNR Square Pvt Ltd · 128 homes · 1.00 acres · 4 towers · Anekal
Delivered late Completed: the builder filed for completion on 4 Nov 2022, 1,404 days after the date it first promised.
At a glance
The builder filed for completion on 4 Nov 2022, 1,404 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 21% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 5 RERA projects in Bengaluru Urban: 0 delivered on time, 3 late (after the date first promised), 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started5 May 2014
- Approved by RERA8 Dec 2017
- First promised31 Dec 2018
The date the builder gave at registration.
- Completion filed4 Nov 2022
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.
Towers
A: 24 homes, 1 basement · B: 32 homes, 1 basement · C: 32 homes, 1 basement · D: 40 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Swimming Pool
- Gym
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.00 acres
- Ground covered by buildings
- 69% of the land
4,047 m²
2,797 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 5 RERA projects of SNR SQUARE PVT LTD on the map
The company
- Registered as
- SNR Square Pvt Ltd
- Type
- Company
- Company number
- U45201KA2014PTC074103
- PAN
- AAUCS3879G
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/171208/002181 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Delay in possession, agreement breach, sale area dispute 15 Feb 2021 · Disposed Authority Bench4
- Amenities pending & RERA registration expired 1 Mar 2021 · Disposed Authority Bench5
- Celing (roof) and walls waterproofing is not completed for Flat A302 SNR Verity 7 Nov 2022 · Disposed Authority Bench4
- Ceiling (roof) and walls waterproofing is not completed for Flat A302 SNR Verity 22 May 2023 · Disposed Authority Bench5
- Water seepage Issues 5 Oct 2023 · Disposed Authority Bench5
- WATER SEEPAGE FROM ROOF AND ALL THE WALLS, CRACKS APPEARED ON ALL THE WALLS SOON AFTER THE ALLOTMENT, 27 Nov 2023 · Disposed Ao
- Ceiling Leakage in All Rooms of the top Floor Flat/in All Flats and major cracks on the Ceiling and walls Full compensation sought as builder unable to fix roof leakage problem 16 May 2024 · Disposed Authority Bench5
- Requesting to refund full amount with interest and loan interest as after taking house we are suffering from mental, emotional and physical threats in unleavable life threatening condition 4 Jun 2024 · Disposed Authority Bench5
Documents
72 files on the RERA page: Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹8.0 cr
- Construction
- ₹14.0 cr
- Total project cost
- ₹22.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.