RERA project · Residential/Group Housing

SLV GOLDEN TOWERS

by SLV Developers Pvt Ltd · 242 homes · 3.12 acres · 2 towers · Bengaluru North

Upcoming Under construction, due Apr 2029. 21% built with 46% of the time used. 12% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
21% built

Due 1 Apr 2029. 46% of the time from RERA approval to the deadline has passed.

Built21%
Time used46%
How much is sold?214 left
12% booked

28 of 242 homes, as the builder reported for Q3 2025-26.

How crowded is it?About the same
77 homes per acre

Similar projects within 3 km: 79 per acre. 75% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 3 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?3 due so far
0% on time

Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 3 late (after the date first promised), 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Jul 2024
  2. Approved by RERA5 Oct 2024
  3. Today24 Oct 2026

    46% of the time to the deadline has passed.

  4. If it slips like a typical project1 Jan 2030

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2621%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q3 2025-26

Slv Kingdom Block A21%
Slv Kingdom Block B21%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

28 booked214 leftQ3 2025-26

Still available: 46 × 2 BHK, 139 × 3 BHK, 20 × 4 BHK, 9 × 2.5 BHK.

Booked, by type

2 BHK9 of 55
3 BHK15 of 154
4 BHK2 of 22
2.5 BHK2 of 11

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,095 sq ft
102 m² carpet · sizes 986–1,168 sq ft (77 at this size)
53 m² land share · 1 parking space
154 homes · 64% of the project
2 BHK
759 sq ft
70 m² carpet · sizes 759–854 sq ft (44 at this size)
38 m² land share · 1 parking space
55 homes · 23% of the project
4 BHK
1,460 sq ft
136 m² carpet
71 m² land share · 1 parking space
22 homes · 9% of the project
2.5 BHK
913 sq ft
85 m² carpet
46 m² land share · 1 parking space
11 homes · 5% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Slv Kingdom Block A10 floors
Slv Kingdom Block B10 floors

Slv Kingdom Block A: 121 homes, 37 m tall, 1 basement · Slv Kingdom Block B: 121 homes, 37 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project77
Typical within 3 km (45)79
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project75%
Typical within 3 km (46)60%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.12 acres

12,646 m²

Ground covered by buildings
25% of the land

3,133 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.13 per home

273 covered, 0 open

Built-up area, all floors
4,15,336 sq ft

38,586 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 4 RERA projects of SLV DEVELOPERS PRIVATE LIMITED on the map

Complaints to RERA about its other projects

The company

Registered as
SLV Developers Pvt Ltd
Type
Company
PAN
AATCS3798R
GSTIN
29AATCS3798R1ZR
Website
http://www.slvdevelopers.com

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹4.7 crBuilding and development ₹97.8 crTotal ₹102.5 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹12.2 cr₹18.4 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station11.91 kmReliable
  • Nearest railway station1.99 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km2Caveat
  • Nearest lake / water body (≥2 ha)1.05 kmCaveat

Hospitals

  • Nearest hospital0.37 kmCaveat

Schools

  • Schools in pincode 560064 (UDISE+ census)240Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km11Caveat
  • Median pupil-teacher ratio, schools within 1 km25 :1Caveat
  • Schools with library + playground + ICT lab (1 km)7Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionYelahanka PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well16.2 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)4.37 kmReliable
  • Nearest sewage treatment plant1.31 kmCaveat
  • Industrial zones within 1 km3Caveat
  • Nearest airfield runway (any, incl. military)2.28 kmCaveat
  • Nearest commercial-airport runway12.19 kmReliable
  • Distance to runway approach-path proxy6.87 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (13.11525, 77.60701), 2026-10-24. Each figure's source and caveat are in the full report.