RERA project · Residential/Group Housing

Skylark Ithaca

by Ithaca Estates Private Limited · 1,761 homes · 19.67 acres · 19 towers · Bengaluru East

Upcoming Under construction, due Dec 2030, after an extension. 34% built with 69% of the time used. 57% of homes booked.

Location report

At a glance

Is it on schedule?Deadline extended
34% built

Due 31 Dec 2030. 69% of the time from RERA approval to the deadline has passed.

Built34%
Time used69%
How much is sold?763 left
57% booked

998 of 1,761 homes, as the builder reported for Q3 2025-26.

How crowded is it?More crowded
90 homes per acre

Similar projects across the city: 76 per acre. 85% of the land is left open.

Any complaints?See the list
144 complaints

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?Litigation
Declared

The builder declares litigation on the land or the project.

What is the builder's record?Too early to tell
No deliveries yet

None of its 2 RERA projects in Bengaluru Urban has reached its deadline yet.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started25 Aug 2014
  2. Approved by RERA15 Sep 2017
  3. First promised31 Dec 2019

    The date the builder gave at registration.

  4. Today24 Oct 2026

    69% of the time to the deadline has passed.

  5. If it slips like a typical project2 Oct 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2634%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q3 2025-26

Tower 150%
Tower 255%
Tower 368%
Tower 462%
Tower 562%
Tower 657%
Tower 752%
Tower 853%
Tower 944%
Tower 1040%
Tower 1138%
Tower 12 (Phase II)2%
Tower 13 (Phase II)2%
Tower 14 (Phase II)2%
Tower 15 (Phase II)2%
Tower 16 (Phase II)2%
Tower 17 (Phase II)2%
Tower 18 (Phase II)2%
Tower 19 (Phase II)2%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

998 booked763 leftQ3 2025-26

Still available: 480 × 2BHK, 214 × 3BHK, 66 × 1BHK, 3 × 4BHK.

Booked, by type

2BHK507 of 987
3BHK344 of 558
1BHK145 of 211
4BHK2 of 5

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2BHK
  • 795 sq ft552 homes73.9 m²
  • 751 sq ft435 homes69.8 m²
Typically 30 m² land share · 1 parking space
987 homes · 56% of the project
3BHK
  • 945 sq ft216 homes87.8 m²
  • 1,212 sq ft160 homes112.6 m²
  • 1,091 sq ft157 homes101.4 m²
  • 1,485 sq ft14 homes138.0 m²
  • and 11 homes in other sizes
Typically 41 m² land share · 1 parking space
558 homes · 32% of the project
1BHK
  • 453 sq ft174 homes42.1 m²
  • 434 sq ft37 homes40.3 m²
Typically 17 m² land share · 1 parking space
211 homes · 12% of the project
4BHK
  • 1,813 sq ft2 homes168.4 m²
  • 2,295 sq ft2 homes213.2 m²
  • 2,054 sq ft1 home190.8 m²
Typically 78 m² land share · 1 parking space
5 homes · 0% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder listed the areas in sq ft; m² figures are converted.

Towers

Tower 119 floors
Tower 219 floors
Tower 319 floors
Tower 419 floors
Tower 519 floors
Tower 619 floors
Tower 719 floors
Tower 819 floors
Tower 919 floors
Tower 1019 floors
Tower 1119 floors
Tower 12 (Phase II)14 floors
Tower 13 (Phase II)14 floors
Tower 14 (Phase II)14 floors
Tower 15 (Phase II)14 floors
Tower 16 (Phase II)14 floors
Tower 17 (Phase II)13 floors
Tower 18 (Phase II)13 floors
Tower 19 (Phase II)13 floors

Tower 1: 113 homes, 2 basements · Tower 2: 115 homes, 2 basements · Tower 3: 115 homes, 2 basements · Tower 4: 75 homes, 2 basements · Tower 5: 115 homes, 2 basements · Tower 6: 115 homes, 2 basements · Tower 7: 76 homes, 2 basements · Tower 8: 79 homes, 2 basements · Tower 9: 116 homes, 2 basements · Tower 10: 117 homes, 2 basements · Tower 11: 115 homes, 2 basements · Tower 12 (Phase II): 89 homes, 2 basements · Tower 13 (Phase II): 89 homes, 2 basements · Tower 14 (Phase II): 89 homes, 2 basements · Tower 15 (Phase II): 89 homes, 2 basements · Tower 16 (Phase II): 89 homes, 2 basements · Tower 17 (Phase II): 55 homes, 2 basements · Tower 18 (Phase II): 55 homes, 2 basements · Tower 19 (Phase II): 55 homes, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project90
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project85%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
19.67 acres

79,621 m²

Ground covered by buildings
15% of the land

12,051 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of Ithaca Estates Private Limited on the map

Complaints to RERA about its other projects

The company

Registered as
Ithaca Estates Private Limited
Type
Company
Company number
U45205KA2013PTC067632

CIN or LLPIN, from the Registrar of Companies.

PAN
AADCI1447B

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹12.7 cr
Construction
₹751.6 cr
Total project cost
₹764.3 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.