RERA project · Residential/Group Housing
SJR PRIMECORPORATION PVT LTD Palazzacity
by SJR PRIMECORPORATION PVT LTD · 340 homes · 10.55 acres · 4 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 5 Jun 2019, 180 days after the date it first promised.
At a glance
The builder filed for completion on 5 Jun 2019, 180 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 84% of the land is left open.
Complaints to RERA about this project. 42 more about the builder's other projects.
The RERA page doesn't say.
Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 4 late (after the date first promised).
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started7 Dec 2013
- Approved by RERA8 Dec 2017
- First promised7 Dec 2018
The date the builder gave at registration.
- Completion filed5 Jun 2019
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 478 sq ft113 homes44.4 m²
- 497 sq ft1 home46.2 m²
- 595 sq ft1 home55.3 m²
- 1,085 sq ft18 homes100.8 m²
- 1,108 sq ft18 homes102.9 m²
- 1,215 sq ft18 homes112.9 m²
- 1,256 sq ft18 homes116.7 m²
- and 35 homes in other sizes
- 854 sq ft36 homes79.3 m²
- 949 sq ft35 homes88.2 m²
- 1,170 sq ft35 homes108.7 m²
- 1,443 sq ft1 home134.1 m²
- 1,461 sq ft1 home135.7 m²
- 1,579 sq ft1 home146.7 m²
- 1,607 sq ft1 home149.3 m²
- and 8 homes in other sizes
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Sears: 76 homes, 2 basements · Taipei: 75 homes, 2 basements · The Burj: 76 homes, 2 basements · Westminster: 113 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 10.55 acres
- Ground covered by buildings
- 16% of the land
42,705 m²
6,906 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 4 RERA projects of SJR PRIMECORPORATION PVT LTD on the map
Complaints to RERA about its other projects
42 complaints across 10 projects. The most complained about:
- Blue Waters Phase 1 17 complaints
- SJR PRIMECORPORATION PVT LTD PALAZZA PH3 7 complaints
- SJR PRIMECORPOATION PVT LTD BLUE WATER PH2 6 complaints
- SJR Prime Corporation Pvt Ltd Blue Water PH 3 5 complaints
- SJR PRIMECORPORATION PVT LTD PALAZZA PH2 2 complaints
Show all 10 projects
- SJR PRIME CORPORATION PVT LTD BLUE WATER PH 3 1 complaint
- 'Blue Waters' by SJR Prime Corporation 1 complaint
- Blue Waters' by SJR Prime Corporation 1 complaint
- Blue Waters by SJR Prime Corporation Pvt Ltd 1 complaint
- Vogue 1 complaint
The company
- Registered as
- SJR PRIMECORPORATION PVT LTD
- Type
- Company
- Company number
- U45201KA2010PTC052844
- PAN
- AAOCS0238B
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171208/001195 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Compensation for delay in Handing Over and breach of agreement 18 Jun 2021 · Disposed Authority Fullbench
- Delay in Completion and Possession 22 Jun 2021 · Disposed Authority Bench5
- Compensation for delay in Handing Over and breach of agreement 15 Nov 2021 · Disposed Authority Bench4
- Defect Liability for my apartment B-152 8 Jul 2022 · Disposed Ao
- Under construction Tower causing damages to my property 1 Feb 2023 · Disposed Ao
- Dampness issues on the internal walls which is caused post every heavy rain due to major cracks in exterior walls 29 Apr 2023 · Disposed Authority Fullbench
- Cancellation of Illegal Demand 8 Nov 2024 · Disposed Authority Fullbench
Documents
56 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹14.9 cr
- Construction
- ₹348.1 cr
- Total project cost
- ₹363.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.