RERA project · Residential/Group Housing
SHRIRAM SUMMITT
by SHRIRAM PROPERTIES PRIVATE LIMITED · 1,128 homes · 14.03 acres · 21 towers · Anekal
Past due, no completion filed Past its deadline of 30 Sep 2021, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Sep 2021, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 79% of the land is left open.
Complaints to RERA about this project. 23 more about the builder's other projects.
The RERA page doesn't say.
Of its 32 RERA projects in Bengaluru Urban: 4 delivered on time, 7 late (after the date first promised), 15 past due with no completion filed, 6 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started2 Jul 2014
- Approved by RERA15 Oct 2017
- First promised31 Dec 2019
The date the builder gave at registration.
- Deadline (extended)30 Sep 2021
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
1: 52 homes, 2 basements · 2: 52 homes, 2 basements · 3: 56 homes, 2 basements · 4: 52 homes, 2 basements · 5: 48 homes, 2 basements · 6: 52 homes, 2 basements · 7: 56 homes, 2 basements · 8: 52 homes, 2 basements · 9: 52 homes, 2 basements · 10: 48 homes, 2 basements · 11: 56 homes, 2 basements · 12: 56 homes, 2 basements · 13: 56 homes, 2 basements · 14: 56 homes, 2 basements · 15: 56 homes, 2 basements · 16: 56 homes, 2 basements · 17: 56 homes, 2 basements · 18: 56 homes, 2 basements · 19: 48 homes, 2 basements · 20: 56 homes, 2 basements · 21: 56 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 14.03 acres
- Ground covered by buildings
- 24% of the land
56,792 m²
13,391 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 32 RERA projects of Shriram Properties on the map
Complaints to RERA about its other projects
23 complaints across 6 projects. The most complained about:
- SHRIRAM MYSTIQUE 11 complaints
- SHRIRAM SAMEEKSHA 3 complaints
- SHRIRAM SAPPHIRE 3 complaints
- SHRIRAM SONGS OF THE EARTH 3 complaints
- Shriram Solitaire 2 complaints
Show all 6 projects
- SHRIRAM SERENITY 1 complaint
The company
- Registered as
- SHRIRAM PROPERTIES PRIVATE LIMITED
- Type
- Company
- Company number
- U72200TN2000PTC044560
- PAN
- AAFCS5801D
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/171015/001121 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Project delayed by 2 years and we end up paying huge amounts towards GST and additional interest, now builder is silent on compensation under RERA act even after promising over mail. 14 Feb 2019 · Disposed Ao
- DELAY COMPENSATION 17 Feb 2019 · Disposed Ao
- Project delay compensation 23 Feb 2019 · Disposed Ao
- Project Delay compensation 3 Mar 2019 · Disposed Ao
- Request for delay compensation as per RERA guidelines because of inordinate delay by the builder in handing over the flat # 05.08.04 in shriram summitt. 11 Mar 2019 · Disposed Ao
- Shriram Summitt - Seeking Compensation for Delay in Handing over the Flat (16-07-03) 14 Mar 2019 · Disposed Ao
- Delay Compensation post delivery date expiry till I get the OC for flat 05-06-02 14 Apr 2019 · Disposed Ao
- Request for compensation on account of delayed possession by builder 26 Apr 2019 · Disposed Ao
- Request for compensation on account of delayed possession by builder. Property: Flat no. 12-04-02, Shriram Summitt, Electronic City, Bangalore. 28 Apr 2019 · Disposed Ao
- Shriram Summitt delayed compensation 28 May 2019 · Disposed Ao
- Compensation for delayed project 14 Jun 2019 · Disposed Ao
- Seeking delay compensation with respect to the flat unit 050904 purchased by me in Shriram Summitt as per RERA rules/norms. 16 Jun 2019 · Disposed Ao
- Delay Compensation 17 Jun 2019 · Disposed Ao
- Seeking delay compensation with respect to the flat no 15 09 01 purchased by me in Shriram Summitt as per RERA rules 28 Jul 2019 · Disposed Ao
- REQUEST FOR DELAY COMPENSATION AS PER RERA KARNATAKA GUIDELINES DUE TO INORDINATE DELAY IN HANDING OVER OF MY FLAT 11.09.04 BY PROMOTER 14 Aug 2019 · Disposed Ao
- Seeking Delay Compensation in lieu of delay in hand over of unit 11 11 02 as per RERA guidelines 20 Aug 2019 · Disposed Ao
- DELAY COMPENSATION 19 Sep 2019 · Disposed Ao
- Claim of Delay Compensation For Project Delay as per RERA 21 Sep 2019 · Disposed Ao
- Project delay compensation as per RERA 24 Sep 2019 · Disposed Ao
- Payment of Delay Compensation as per RERA 28 Sep 2019 · Disposed Ao
- Claim for delay compensation,GST INPUT & Interest 6 Oct 2019 · Disposed Ao
- Relief Sought from RERA: Delay Compensation as per Agreement and RERA Rules 1 Nov 2019 · Disposed Ao
- seeking for delay compensation from the date of default till the date of Handover of possession 12 Nov 2019 · Disposed Ao
- Return of delay compensation 21 Nov 2019 · Disposed Ao
- Physical Possession , OC & Delay Compensation 7 Mar 2020 · Disposed Authority Bench5
- Refund of Project Delay Compensation 16 Mar 2020 · Disposed Authority Bench5
- Delay Compensation Not Paid by Shriram Properties (Shriram Summitt Project) 17 Mar 2020 · Disposed Authority Bench5
- Promoter should pay the interest till they handover the flat to me. 19 Mar 2020 · Disposed Authority Bench6
- Project is Delayed and also no updates on RERA extension and latest delivery date 15 Sep 2020 · Disposed Authority Bench5
- Delay in Possession starting 31-Dec-2019 & absolutely no compensation provided by builder. 26 Sep 2020 · Disposed Authority Bench5
- Delay in Possession starting 31-Dec-2019 & absolutely no compensation provided by builder 29 Sep 2020 · Disposed Authority Bench5
- Delay in Possession starting 31-Dec-2019 & no compensation provided by builder. 8 Nov 2020 · Disposed Authority Bench5
- Delay in Possession (31-Dec-2019) & No Compensation provisioned by builder. 15 Nov 2020 · Disposed Authority Bench5
- Complaint under Section 31 of the Real Estate Regulation and Development Act, 2016 14 Dec 2020 · Disposed Authority Bench5
- Cancellation Of Agreement - Shriram Summit 21.14.03 11 Feb 2021 · Disposed Authority Bench5
- Requesting Refund for delayed project 16 May 2021 · Disposed Authority Bench5
- delayed handover by 24 months 18 May 2021 · Disposed Authority Bench5
- Delay in handover of 2 units and lack of commitment on compensation 24 May 2021 · Disposed Authority Bench5
- REFUND OR COMPENSATION 25 May 2021 · Disposed Authority Bench5
- Delivery Date Expired 25 May 2021 · Disposed Authority Bench5
- Compensation and delivery of the Apartment 26 May 2021 · Disposed Authority Bench5
- Compensation Needed for the Delay and Trauma Caused by Builder by NOT Meeting the Project Timeline 26 May 2021 · Disposed Ao
- Delayed Delivery and No clarity on Compensation( Flat No 210402) 26 May 2021 · Disposed Authority Bench5
- Delay Compensation 27 May 2021 · Disposed Authority Bench5
- Refund or Delay Compensation. 30 May 2021 · Disposed Authority Bench5
- Delivery of Project and Compensation for non Delivery on time 7 Jun 2021 · Disposed Authority Bench5
- Delay in possession(31st dec 2019) and no compensation payed by builder 13 Jun 2021 · Disposed Ao
- Project Delay 13 Jun 2021 · Disposed Authority Bench5
- Delay in handover of flat(Agreement completion date:31st Dec 2019) and no compensation from builder 13 Jun 2021 · Disposed Authority Bench5
- Builder is not delivering the project and denying for delay compensation 15 Jun 2021 · Disposed Authority Bench5
- Compensation on Account of Delay in Possession 15 Jun 2021 · Disposed Authority Bench5
- Multiple extension in Delivery date of Project Completion and compensation for delay 23 Jun 2021 · Disposed Authority Bench5
- Delay in Flat Handover 23 Jun 2021 · Disposed Authority Bench5
- Delay in possession(31st dec 2019) and no compensation payed by builder 5 Jul 2021 · Disposed Ao
- Need the delay compensation as project is getting delay for more that 2 yrs as per Sales Agreement. 6 Jul 2021 · Disposed Authority Bench5
- Delayed Compensation 14 Jul 2021 · Disposed Authority Bench5
- delayed, compensation or Bank Interest payout until Possession. 17 Jul 2021 · Disposed Authority Bench5
- Shriram Summit Project Delayed 18 Jul 2021 · Disposed Authority Bench5
- Delay in Possession and compensation is not provided by builder 9 Aug 2021 · Disposed Authority Bench5
- Multiple extension in Delivery date of Project Completion and compensation for delay 19 Aug 2021 · Disposed Authority Bench5
- Delay in Possession, Pre-EMI Interest and compensation is not provided by builder 25 Aug 2021 · Disposed Authority Bench5
- Delay compensation and completion of project 30 Aug 2021 · Disposed Authority Bench5
- Delivery Date Delayed by almost 2 years & False promises given 1 Sep 2021 · Disposed Authority Bench5
- Refund or Proper Compensation for Delayed Project 26 Sep 2021 · Disposed Authority Bench5
- Delay in possession(31st December 2019) and no compensation payed by Builder 8 Nov 2021 · Disposed Ao
- Exorbitant Delay in Possession (3yrs of Delay) 22 Dec 2021 · Disposed Authority Bench5
- Delay in possession and requesting compensation from the builder for the delay 22 Dec 2021 · Disposed Authority Bench6
- Delay in Project Completion, Failed to adhere to RERA guidelines, No update on compensation 28 Mar 2022 · Disposed Authority Bench6
- Delay in Handover of Flat 211204 ( Compensation Requested ) by SHRIRAM PROPERTIES PRIVATE LIMITED Registration Number : PRM/KA/RERA/1251/308/PR/171015/001121 28 Mar 2022 · Disposed Authority Bench6
- Immediate intervention on Compensation and aparment handover date 29 Mar 2022 · Disposed Authority Bench6
- Delay compensation and Handover of our flat 29 Mar 2022 · Disposed Authority Bench6
- Request for compensation on account of delayed possession by builder. Property: Flat no. 21:03:02, Shriram Summit, Electronic City, Bangalore. 30 Mar 2022 · Disposed Authority Bench6
- Request for compensation for delayed project Flat no 19.08.03. Shriram Summit, electronic city, Bengaluru 1 Apr 2022 · Disposed Authority Bench6
- Project Shriram Summit is being delayed and no compnesation from builder. 26 Apr 2022 · Disposed Authority Bench6
- Delay in project compensation and flat delivery 4 May 2022 · Disposed Authority Bench6
- Excessive Delay in Handover & Not providing Delay Compensation 16 May 2022 · Disposed Authority Bench6
- Request for Compensation for too much delay in handover of Property SHRIRAM SUMMITT WING 19.09.903 18 May 2022 · Disposed Authority Bench6
- Delay in Project and compensation for the delay from RERA 17 Jun 2022 · Disposed Authority Bench6
- Builder denied any delay compensation as project is delayed more the 2 year and 6 monts 25 Jun 2022 · Disposed Authority Bench6
- Request for Delay compensation on account of delayed possession by builder for Property: Flat no. 21:11:02, Shriram Summit, Electronic City, Bangalore. 28 Jul 2022 · Disposed Authority Bench6
- Delayed delivery of flat and unreasonable payment-delay fee charged by builder 1 Aug 2022 · Disposed Authority Bench6
- Requisition for Delay Compensation for late project delivery of Shriram Summitt SMT 201401 by the builder Shriram Properties Pvt Ltd 3 Aug 2022 · Disposed Authority Bench6
- Compensation on the late handing of the Apartment 8 Nov 2022 · Disposed Authority Bench6
- Delay in possession 16 Nov 2022 · Disposed Authority Bench6
- Request for Delay Compensation Claim for Late Handover of Purchased Property 22 Nov 2022 · Disposed Authority Bench6
- Delay in handing over of our Flat 06.14.01 due to non rectification of snags and compensation for interest paid to bank 30 Jan 2023 · Disposed Authority Bench6
- Compensation on delay of delivery of flat 28 Jun 2023 · Disposed Authority Bench6
- Unlawful Demand and Penalty notice issued by the Promotor 28 Jun 2023 · Disposed Authority Bench6
- Delay in Flat handover 8 Aug 2023 · Disposed Authority Bench6
- Need the delay compensation as project got delay for 2.5 yrs as per Sales Agreement. 25 Aug 2023 · Disposed Authority Bench6
- Delay Compensaction 1 Sep 2023 · Disposed Authority Bench6
- Delayed compensation 4 Sep 2023 · Disposed Authority Bench6
- NON PAYMENT OF DELAY COMPENSATION 12 Sep 2023 · Disposed Authority Bench6
- Compensation on delay period interest for delayed handover of the flat 22 Nov 2023 · Disposed Authority Bench6
- Delay in possession 13 Aug 2024 · Disposed Authority Bench5
- delay in possession 18 Jun 2025 · Disposed Authority Bench5
- Immediate corpus transfer with interest including handover of audited accounts and documents plus penalities 10 Nov 2025 · Disposed Authority Bench5
- For Payment of Compensation and interest for delay in delivery of possession of the flat 14 Nov 2025 · Disposed Authority Bench5
- Request for Interest on delayed period for 2 and half year approx 27 Apr 2026 · Under Enquiry Authority Bench5
- For Payment of Compensation and delay period interest in delivery of possession of the flat 2 Sep 2026 · Under Enquiry Authority Bench5
Documents
110 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹5.0 cr
- Construction
- ₹397.5 cr
- Total project cost
- ₹402.6 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.