Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

SHRIRAM SOUTHERN CREST - Phase -2

by SHRIPROP PROJECTS PRIVATE LIMITED · 75 homes · 3.72 acres · 4 towers · Bengaluru South

Past due, no completion filed Past its deadline of 21 Oct 2026, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 21 Oct 2026, and no completion is filed.

How much is sold?0 left
100% booked

75 of 75 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
20 homes per acre

Similar projects within 3 km: 73 per acre. 72% of the land is left open.

Any complaints?See the list
3 complaints

Complaints to RERA about this project. 17 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?26 due so far
15% on time

Of its 32 RERA projects in Bengaluru Urban: 4 delivered on time, 7 late (after the date first promised), 15 past due with no completion filed, 6 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started22 Jan 2020
  2. Approved by RERA10 Mar 2020
  3. First promised21 Jan 2025

    The date the builder gave at registration.

  4. Deadline (extended)21 Oct 2026

    Passed with no completion filed.

How much is built, each quarter

Q3 2025-26100%
Q4 2025-26100%
Q1 2026-27100%
Q2 2026-27100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower A100%
Tower B100%
Tower C100%
Tower D100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

75 booked0 leftQ2 2026-27

Booked, by type

2 + Study57 of 57
2 BHK8 of 8
3 + Study2 of 2
3 BHK8 of 8

Booked, each quarter

Q3 2025-2675 of 75
Q4 2025-2675 of 75
Q1 2026-2775 of 75
Q2 2026-2775 of 75

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2 + Study
  • 970 sq ft51 homes90.1 m²
  • 995 sq ft6 homes92.4 m²
Typically 11 m² balcony/terrace · 1 parking space
57 homes · 76% of the project
2 BHK
  • 892 sq ft8 homes82.9 m²
Typically 7 m² balcony/terrace · 1 parking space
8 homes · 11% of the project
3 BHK
  • 1,218 sq ft8 homes113.2 m²
Typically 10 m² balcony/terrace · 1 parking space
8 homes · 11% of the project
3 + Study
  • 1,340 sq ft2 homes124.5 m²
Typically 11 m² balcony/terrace · 1 parking space
2 homes · 3% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A18 floors
Tower B18 floors
Tower C18 floors
Tower D17 floors

Tower A: 8 homes, 3 basements · Tower B: 8 homes, 3 basements · Tower C: 8 homes, 3 basements · Tower D: 51 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project20
Typical within 3 km (41)73
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project72%
Typical within 3 km (41)52%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.72 acres

15,074 m²

Ground covered by buildings
24% of the land

3,631 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 32 RERA projects of Shriram Properties on the map

Complaints to RERA about its other projects

The company

Registered as
SHRIPROP PROJECTS PRIVATE LIMITED
Type
Company
Company number
U45202KA2008PTC046145

CIN or LLPIN, from the Registrar of Companies.

PAN
AALCS9017K

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹10.9 cr
Construction
₹39.2 cr
Total project cost
₹50.2 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹0.0 lakh₹0.0 lakh
Q4 2025-26₹0.0 lakh₹0.0 lakh
Q1 2026-27₹0.0 lakh₹0.0 lakh
Q2 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.24 kmReliable
  • Nearest railway station6.78 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km2Caveat
  • Parks within 1 km16Caveat
  • Nearest lake / water body (≥2 ha)1.01 kmCaveat

Hospitals

  • Nearest hospital0.2 kmCaveat

Schools

  • Schools in pincode 560078 (UDISE+ census)117Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km8Caveat
  • Median pupil-teacher ratio, schools within 1 km17.9 :1Caveat
  • Schools with library + playground + ICT lab (1 km)6Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKumaraswamy Layout PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)29 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km4Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.39 kmReliable
  • Nearest sewage treatment plant1.11 kmCaveat
  • Industrial zones within 1 km6Caveat
  • Nearest airfield runway (any, incl. military)10.1 kmCaveat
  • Nearest commercial-airport runway33.91 kmReliable
  • Distance to runway approach-path proxy30.35 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.90562, 77.57202), 2026-10-24. Each figure's source and caveat are in the full report.