RERA project · Plotted Development
Shriram Hamsadhwani Phase 2
by Shriline Properties Pvt Ltd · 14 plots · 0.98 acres · Anekal
Past due, no completion filed Past its deadline of 31 Mar 2023, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Mar 2023, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 16 per acre. 44% of the land is left open.
Complaints to RERA about this project. 2 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started30 May 2022
- Approved by RERA11 Aug 2022
- Deadline31 Mar 2023
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.98 acres
- Plot area (the sites)
- 56% of the land
- Roads
- 1,138 m²
- Parks and open spaces
- 395 m²
- Civic amenity sites
- 199 m²
3,946 m²
2,213 m²
Sites kept for public uses such as a school or a health centre.
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of Shriline properties Pvt.Ltd on the map
Complaints to RERA about its other projects
- Shriline Avanti 2 complaints
The company
- Registered as
- Shriline Properties Pvt Ltd
- Type
- Company
- Company number
- U45202KA2008PTC046717
- PAN
- AAQCS4337K
- GSTIN
- 29AAQCS4337K1ZN
- Website
- www.shriramland.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- Shriline Avanti PRM/KA/RERA/1251/308/PR/171031/001664 · approved 31 Oct 2017
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/110822/005152 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority · APA/LAO/42/2021-22 · 18 Apr 2022
- Litigation on the landNone declared
- Litigation on the projectNot stated
- Water sourceLocal Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
126 files on the RERA page: Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
CaveatCost as certified by the builder's chartered accountant at registration.