RERA project · Residential/Group Housing
SHRIRAM BLUE
by MAARS INFRA DEVELOPERS PRIVATE LIMITED · 471 homes · 8.59 acres · 11 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 6 Oct 2023, 812 days after the date it first promised.
At a glance
The builder filed for completion on 6 Oct 2023, 812 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 80 per acre. 16% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 32 RERA projects in Bengaluru Urban: 4 delivered on time, 7 late (after the date first promised), 15 past due with no completion filed, 6 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started16 Jul 2018
- Approved by RERA28 Jul 2018
- First promised16 Jul 2021
The date the builder gave at registration.
- Completion filed6 Oct 2023
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
A: 42 homes, 1 basement · B: 42 homes, 1 basement · C: 42 homes, 1 basement · D: 42 homes, 1 basement · E: 42 homes, 1 basement · F: 48 homes, 1 basement · G: 42 homes, 1 basement · H: 42 homes, 1 basement · J: 45 homes, 1 basement · K: 42 homes, 1 basement · L: 42 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 8.59 acres
- Ground covered by buildings
- 33% of the land
34,756 m²
11,368 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 32 RERA projects of Shriram Properties on the map
The company
- Registered as
- MAARS INFRA DEVELOPERS PRIVATE LIMITED
- Type
- Company
- Company number
- U70102KA2010PTC052472
- PAN
- AAGCM3849L
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/180728/001966 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Refund of Allotment Amount for Cancelled Booking in SHRIRAM BLUE 28 Mar 2019 · Disposed Ao
- Refund of Allotment Amount for Cancelled Booking in SHRIRAM BLUE 28 Mar 2019 · Disposed Ao
- Booking Cancellation and Paid Amount not being refunded 3 Dec 2019 · Disposed Authority Bench5
- Amount Not refunded 22 Mar 2021 · Disposed Authority
- Compensation due to delay 31 Jan 2023 · Disposed Authority Bench5
- Payment of Delay Interest and Completion of Project on or before 16-April-2023 7 Feb 2023 · Disposed Authority Bench6
- Compensation due to deficiency of service thereby leading to loss of potential income 9 Feb 2023 · Disposed Ao
- Compensation due to delay in possession of unit and completion of Project 22 Feb 2023 · Disposed Authority Bench6
- Compensation for Delay in Completion of Project 22 Feb 2023 · Disposed Authority Bench6
- IMMEDIATE RELEASE OF DELAY INTEREST, COMPLETION OF PROJECT AND POSSESSION OF UNIT ON OR BEFORE 16- APRIL-2023 23 Feb 2023 · Disposed Authority Bench6
- Compensation due to delay in possession of unit and completion of Project 24 Feb 2023 · Disposed Authority Bench6
- Compensation due to delay in possession of unit and completion of Project 24 Feb 2023 · Disposed Authority Bench6
- Delay in possession of the flat which led to further expenses to us and mental trauma 27 Feb 2023 · Disposed Authority Bench6
- Compensation for delay in delivery of the apartment and breach of sale agreement 14 Mar 2023 · Disposed Authority Bench6
- Project delayed by almost 2 year, compensation required 16 Mar 2023 · Disposed Authority Bench6
- Tiles in lieu of Wooden Flooring in Tower F 3 Apr 2023 · Disposed Authority Bench6
- Compensation for delay in completion of Project Shriram Blue and handover of our unit B0802 15 Apr 2023 · Disposed Authority Bench5
- Request for compensation for delay in handover and take action against builder for denying of compensation as per agreement terms 18 Apr 2023 · Disposed Authority Bench5
- Compensation for Delay in Project Completion and Flat Handover 20 Apr 2023 · Disposed Authority Bench5
- Delay in Project Handover and almost nil compensation 25 Apr 2023 · Disposed Authority Bench5
- Builder wrongfully requesting permission for RERA extension 8 May 2023 · Disposed Authority Bench6
- Compensation for delay in possession for my apartment 9 May 2023 · Disposed Authority Bench6
- Compensation for Delayed Possession of Flat in Shriram Blue 18 May 2023 · Disposed Authority Bench6
- Request for compensation because of delay in handover of apartment within agreed completion time 30 May 2023 · Disposed Authority Bench6
- Failed to deliver unit i.e C block 602 since April 2022 till Now 7 Jun 2023 · Disposed Authority Bench6
- Compensation on Delay and Breach of Agreement 13 Jul 2023 · Disposed Authority Bench6
- Delay in delivery Interest 21 Sep 2023 · Disposed Authority Bench6
- Form N - delay in delivering the posession 11 Jan 2024 · Disposed Authority Bench4
- Interest on delay period 7 Mar 2024 · Disposed Authority Bench6
- Request for Inspection and Verification of All Promised Amenities and Deliverables in Shriram Blue Society by Shriram Group 17 Sep 2024 · Disposed Authority Fullbench
- Claiming the interest for Delay possession 19 Nov 2024 · Disposed Authority Fullbench
- Delay in Handing over unit 30 Jun 2025 · Disposed Authority Fullbench
Documents
115 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹9.2 cr
- Construction
- ₹319.8 cr
- Total project cost
- ₹329.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station3.19 kmReliable
- Nearest railway station4.13 kmReliable
- Bus stops within 500 m1Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km1Caveat
- Nearest lake / water body (≥2 ha)1.58 kmCaveat
Hospitals
- Nearest hospital1.25 kmCaveat
Schools
- Schools in pincode 560036 (UDISE+ census)89Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionK.R. Puram PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km4Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)7.4 kmReliable
- Nearest sewage treatment plant1.19 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)8.49 kmCaveat
- Nearest commercial-airport runway19.28 kmReliable
- Distance to runway approach-path proxy18.59 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (13.01496, 77.72839), 2026-10-24. Each figure's source and caveat are in the full report.