Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

SHILPA RATHNA

by SHILPA HIGH RISE PRIVATE LIMITED · 110 homes · 1.62 acres · 1 tower · Bengaluru East

Upcoming Under construction, due Jan 2027. 97% built with 92% of the time used. 60% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
97% built

Due 14 Jan 2027. 92% of the time from RERA approval to the deadline has passed.

Built97%
Time used92%
How much is sold?44 left
60% booked

66 of 110 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
68 homes per acre

Similar projects across the city: 76 per acre. 52% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA28 Mar 2024
  2. Work started1 Apr 2024
  3. Today24 Oct 2026

    92% of the time to the deadline has passed.

  4. If it slips like a typical project16 Oct 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2676%
Q4 2025-2685%
Q1 2026-2792%
Q2 2026-2797%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

66 booked44 leftQ2 2026-27

Still available: 18 × 2 BHK, 26 × 3 BHK.

Booked, by type

2 BHK30 of 48
3 BHK36 of 62

Booked, each quarter

Q3 2025-2666 of 110
Q4 2025-2666 of 110
Q1 2026-2766 of 110
Q2 2026-2766 of 110

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,175 sq ft
109 m² carpet · sizes 1,175–1,356 sq ft (15 at this size)
68 m² land share · 7 m² balcony/terrace · 2 parking spaces
62 homes · 56% of the project
2 BHK
874 sq ft
81 m² carpet · sizes 865–886 sq ft (35 at this size)
48 m² land share · 5 m² balcony/terrace · 1 parking space
48 homes · 44% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Shilpa Rathna8 floors

Shilpa Rathna: 110 homes, 30 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project68
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project52%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.62 acres

6,550 m²

Ground covered by buildings
48% of the land

3,139 m²

Floor-area ratio
2.24

Floors built per unit of land: 2.24 m² of floors for each m² of land.

Parking
1.60 per home

176 covered, 0 open

Built-up area, all floors
2,52,134 sq ft

23,424 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
SHILPA HIGH RISE PRIVATE LIMITED
Type
Company
Company number
U45209KA2012PTC067098

CIN or LLPIN, from the Registrar of Companies.

PAN
AASCS4061L
GSTIN
29AASCS4061L1ZM

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹29.9 crBuilding and development ₹43.7 crTotal ₹73.6 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹4.0 cr₹5.5 cr
Q4 2025-26₹4.4 cr₹6.9 cr
Q1 2026-27₹1.3 cr₹11.2 cr
Q2 2026-27₹1.4 cr₹3.3 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station10.35 kmReliable
  • Nearest railway station12.19 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)2.01 kmCaveat

Hospitals

  • Nearest hospital2.63 kmCaveat

Schools

  • Schools in pincode 562130 (UDISE+ census)148Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionMadhanayakanahally PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)20.43 kmReliable
  • Nearest sewage treatment plant7.06 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)23.2 kmCaveat
  • Nearest commercial-airport runway38.05 kmReliable
  • Distance to runway approach-path proxy30.71 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (13.00200, 77.39590), 2026-10-24. Each figure's source and caveat are in the full report.