RERA project · Residential/Group Housing
SEASONS AVENUE
by ASIT MAVJIBHAI LAKUM · 84 homes · 0.80 acres · 1 tower · Bengaluru North
Upcoming Under construction, due Dec 2028, after an extension. 61% built with 80% of the time used. 5% of homes booked.
At a glance
Due 31 Dec 2028. 80% of the time from RERA approval to the deadline has passed.
18 of 336 homes, as the builder reported for Q2 2026-27.
Similar projects across the city: 76 per acre. 44% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started5 Jul 2017
- Approved by RERA20 Jan 2018
- First promised30 Jun 2022
The date the builder gave at registration.
- Today24 Oct 2026
80% of the time to the deadline has passed.
- Deadline (extended)31 Dec 2028
The date it must be complete by.
- If it slips like a typical project2 Oct 2029
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 112 × 1BHK, 206 × 2BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 955 sq ft4 homes88.7 m²
- 945 sq ft3 homes87.8 m²
- 1,027 sq ft3 homes95.4 m²
- 1,114 sq ft3 homes103.5 m²
- and 19 homes in other sizes
- 628 sq ft5 homes58.3 m²
- 644 sq ft5 homes59.8 m²
- 645 sq ft3 homes59.9 m²
- 647 sq ft3 homes60.1 m²
- and 5 homes in other sizes
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Seasons Avenue: 84 homes
Amenities
- Electricity
- CCTV Surveillance
- Power Backup
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.80 acres
- Ground covered by buildings
- 56% of the land
3,237 m²
1,827 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- ASIT MAVJIBHAI LAKUM
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/309/PR/180120/001585 · Approved
- Building plan approvedBIAPPA - Bangalore Airport Area Planning Authority
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q2 2026-27 update
Complaints to RERA about this project
None on RERA Karnataka.
Documents
79 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹3.3 cr
- Construction
- ₹11.6 cr
- Total project cost
- ₹14.9 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹17.2 lakh | ₹17.2 lakh |
| Q4 2025-26 | ₹10.3 lakh | ₹10.3 lakh |
| Q1 2026-27 | ₹1.1 cr | ₹1.1 cr |
| Q2 2026-27 | ₹1.2 cr | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.