Upcoming Under construction, due Dec 2027. 60% built with 71% of the time used. 62% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
60% built

Due 31 Dec 2027. 71% of the time from RERA approval to the deadline has passed.

Built60%
Time used71%
How much is sold?40 left
62% booked

64 of 104 homes, as the builder reported for Q4 2025-26.

How crowded is it?Less crowded
45 homes per acre

Similar projects within 3 km: 80 per acre. 62% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started19 Oct 2023
  2. Approved by RERA9 Nov 2023
  3. Today24 Oct 2026

    71% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2660%
Q4 2025-2660%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q4 2025-26

Block A60%
Block B60%
Block C60%
Block D60%
Block E60%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

64 booked40 leftQ4 2025-26

Still available: 40 × 3 BHK.

Booked, by type

3 BHK64 of 104

Booked, each quarter

Q3 2025-2663 of 104
Q4 2025-2664 of 104

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,249 sq ft
116 m² carpet · sizes 764–1,690 sq ft (42 at this size)
88 m² land share · 1 parking space
104 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block A5 floors
Block B5 floors
Block C5 floors
Block D5 floors
Block E5 floors

Block A: 25 homes, 15 m tall, 1 basement · Block B: 25 homes, 15 m tall, 1 basement · Block C: 22 homes, 15 m tall, 1 basement · Block D: 15 homes, 15 m tall, 1 basement · Block E: 17 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project45
Typical within 3 km (67)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project62%
Typical within 3 km (66)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.31 acres

9,359 m²

Ground covered by buildings
38% of the land

3,591 m²

Floor-area ratio
1.75

Floors built per unit of land: 1.75 m² of floors for each m² of land.

Parking
1.11 per home

115 covered, 0 open

Built-up area, all floors
2,36,892 sq ft

22,008 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
SBR INFRA
Type
Partnership Firm
PAN
AEWFS4345G

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹20.5 crBuilding and development ₹78.2 crTotal ₹98.8 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹7.1 cr₹5.0 cr
Q4 2025-26₹4.0 cr₹2.8 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.72 kmReliable
  • Nearest railway station1.54 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)1.6 kmCaveat

Hospitals

  • Nearest hospital0.56 kmCaveat

Schools

  • Schools in pincode 560067 (UDISE+ census)57Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km8Caveat
  • Median pupil-teacher ratio, schools within 1 km21.6 :1Caveat
  • Schools with library + playground + ICT lab (1 km)6Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKadugodi PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well60.8 m below groundCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.76 kmReliable
  • Nearest sewage treatment plant2.04 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)4.96 kmCaveat
  • Nearest commercial-airport runway20.23 kmReliable
  • Distance to runway approach-path proxy18.61 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.01009, 77.76416), 2026-10-24. Each figure's source and caveat are in the full report.