RERA project · Residential/Group Housing

Saideep Hiranya

by Shri Saideep Srinidhi Buildcon LLP · 145 homes · 2.46 acres · 1 tower · Bengaluru North

Upcoming Under construction, due Dec 2029. 38% built with 26% of the time used. 24% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
38% built

Due 31 Dec 2029. 26% of the time from RERA approval to the deadline has passed.

Built38%
Time used26%
How much is sold?110 left
24% booked

35 of 145 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
59 homes per acre

Similar projects within 3 km: 80 per acre. 63% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA4 Sep 2025
  2. Work started15 Sep 2025
  3. Today24 Oct 2026

    26% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2030

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2619%
Q4 2025-2624%
Q1 2026-2729%
Q2 2026-2738%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

35 booked110 leftQ2 2026-27

Still available: 30 × 2 BHK, 17 × 2.5 BHK, 63 × 3 BHK.

Booked, by type

2 BHK15 of 45
2.5 BHK4 of 21
3 BHK16 of 79

Booked, each quarter

Q3 2025-2610 of 145
Q4 2025-2621 of 145
Q1 2026-2724 of 145
Q2 2026-2735 of 145

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,141 sq ft
106 m² carpet · sizes 807–1,195 sq ft (25 at this size)
56 m² land share · 1 parking space
79 homes · 54% of the project
2 BHK
807 sq ft
75 m² carpet · sizes 807–1,130 sq ft (34 at this size)
73 m² land share · 1 parking space
45 homes · 31% of the project
2.5 BHK
1,076 sq ft
100 m² carpet · sizes 1,076–1,087 sq ft (20 at this size)
77 m² land share · 1 parking space
21 homes · 14% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Saideep Hiranya4 floors

Saideep Hiranya: 145 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project59
Typical within 3 km (85)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project63%
Typical within 3 km (85)79%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.46 acres

9,965 m²

Ground covered by buildings
37% of the land

3,701 m²

Floor-area ratio
1.75

Floors built per unit of land: 1.75 m² of floors for each m² of land.

Parking
1.36 per home

191 covered, 5 open

Built-up area, all floors
2,83,381 sq ft

26,327 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
Shri Saideep Srinidhi Buildcon LLP
Type
Partnership Firm
Company number
ACI-1528

CIN or LLPIN, from the Registrar of Companies.

PAN
AFIFS7116Q
GSTIN
29AFIFS7116Q1Z4

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹84.0 crBuilding and development ₹61.3 crTotal ₹149.6 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹1.5 cr₹1.0 cr
Q4 2025-26₹3.5 cr₹3.3 cr
Q1 2026-27₹3.4 cr₹2.6 cr
Q2 2026-27₹6.4 cr₹5.4 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.94 kmReliable
  • Nearest railway station5.93 kmReliable
  • Bus stops within 500 m4Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km15Caveat
  • Parks within 1 km10Caveat
  • Nearest lake / water body (≥2 ha)0.91 kmCaveat

Hospitals

  • Nearest hospital0.03 kmCaveat

Schools

  • Schools in pincode 560066 (UDISE+ census)44Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km6Caveat
  • Median pupil-teacher ratio, schools within 1 km27.3 :1Caveat
  • Schools with library + playground + ICT lab (1 km)2Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionWhitefield PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km2Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well4.5 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)10.22 kmReliable
  • Nearest sewage treatment plant1.3 kmCaveat
  • Industrial zones within 1 km6Caveat
  • Nearest airfield runway (any, incl. military)3.59 kmCaveat
  • Nearest commercial-airport runway25.36 kmReliable
  • Distance to runway approach-path proxy24.78 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat

ReliableFrom our location report at the builder-entered pin (12.96007, 77.71630), 2026-10-24. Each figure's source and caveat are in the full report.