Neighborhood IntelOpen on the map

RERA project · Plotted Development

S V GARDENS

by S.V. BUILDERS & DEVELOPERS · 45 plots · 3.42 acres · Bengaluru South

Delivered on time Completed: the builder filed for completion on 28 Jul 2026, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 28 Jul 2026, by the date it promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?About the same
13 plots per acre

Similar projects within 3 km: 14 per acre. 53% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
50% on time

Of its 2 RERA projects in Bengaluru Urban: 1 delivered on time, 1 past due with no completion filed.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started15 Jan 2024
  2. Approved by RERA5 Jun 2026
  3. Completion filed28 Jul 2026

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

How much is built, each quarter

Q1 2026-27100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

9.14*15.24 Sites
1,499 sq ft
139 m² each
18 plots · 40% of the project
9.14*12.19 Sites
1,195 sq ft
111 m² each
1 plot · 2% of the project
Odd Sites
1,594 sq ft
148 m² each
26 plots · 58% of the project

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Plots per acre

This project13
Typical within 3 km (26)14
Typical in the city (593)16

Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project53%
Typical within 3 km (26)49%
Typical in the city (730)46%

The share of the land not built on, which includes roads.

Land
3.42 acres

13,860 m²

Plot area (the sites)
47% of the land

6,468 m²

Roads
4,881 m²
Parks and open spaces
1,814 m²
Civic amenity sites
698 m²

Sites kept for public uses such as a school or a health centre.

CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of S V BUILDERS AND DEVELOPERS on the map

The company

Registered as
S.V. BUILDERS & DEVELOPERS
Type
Partnership Firm
PAN
ACFFS3440R

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹8.5 crBuilding and development ₹3.1 crTotal ₹11.6 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q1 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station7.87 kmReliable
  • Nearest railway station11.34 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km7Caveat
  • Nearest lake / water body (≥2 ha)0.43 kmCaveat

Hospitals

  • Nearest hospital0.7 kmCaveat

Schools

  • Schools in pincode 560082 (UDISE+ census)71Caveat
  • Median pupil-teacher ratio, schools within 1 km16.5 :1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKaggalipura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)9.64 kmReliable
  • Nearest sewage treatment plant10.52 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)23.38 kmCaveat
  • Nearest commercial-airport runway48.01 kmReliable
  • Distance to runway approach-path proxy43.91 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.79419, 77.50705), 2026-10-24. Each figure's source and caveat are in the full report.