RERA project · Residential/Group Housing

Rohan Ekanta Phase 3

by Rohan Builders · 271 homes · 4.02 acres · 4 towers · Bengaluru East

Upcoming Under construction, due Dec 2028. 65% built with 60% of the time used. 94% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
65% built

Due 31 Dec 2028. 60% of the time from RERA approval to the deadline has passed.

Built65%
Time used60%
How much is sold?16 left
94% booked

255 of 271 homes, as the builder reported for Q1 2026-27.

How crowded is it?Less crowded
68 homes per acre

Similar projects within 3 km: 81 per acre. 82% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?12 due so far
75% on time

Of its 13 RERA projects in Bengaluru Urban: 9 delivered on time, 2 late (after the date first promised), 1 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Jul 2023
  2. Approved by RERA13 Jul 2023
  3. Today24 Oct 2026

    60% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2656%
Q4 2025-2661%
Q1 2026-2765%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q1 2026-27

Wing F100%
Wing G100%
Wing H100%
Wing I100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

255 booked16 leftQ1 2026-27

Still available: 1 × 2 BHK, 15 × 3 BHK.

Booked, by type

2 BHK115 of 116
3 BHK140 of 155

Booked, each quarter

Q3 2025-26243 of 271
Q4 2025-26246 of 271
Q1 2026-27255 of 271

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,028 sq ft
96 m² carpet · sizes 956–1,058 sq ft (24 at this size)
35 m² land share · 9 m² balcony/terrace · 1 parking space
155 homes · 57% of the project
2 BHK
710 sq ft
66 m² carpet · sizes 700–833 sq ft (43 at this size)
26 m² land share · 7 m² balcony/terrace · 1 parking space
116 homes · 43% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Wing F17 floors
Wing G19 floors
Wing H17 floors
Wing I19 floors

Wing F: 65 homes, 54 m tall, 2 basements · Wing G: 72 homes, 60 m tall, 2 basements · Wing H: 64 homes, 54 m tall, 2 basements · Wing I: 70 homes, 60 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project68
Typical within 3 km (132)81
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project82%
Typical within 3 km (132)73%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.02 acres

16,258 m²

Ground covered by buildings
17% of the land

2,842 m²

Floor-area ratio
1.25

Floors built per unit of land: 1.25 m² of floors for each m² of land.

Parking
1.08 per home

271 covered, 22 open

Built-up area, all floors
5,88,882 sq ft

54,709 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 13 RERA projects of Rohan Builders on the map

Complaints to RERA about its other projects

The company

Registered as
Rohan Builders
Type
Partnership Firm
PAN
AABFR4467K
GSTIN
29AABFR4467K1ZQ
Website
https://www.rohanbuilders.com

Its other registrations on RERA Karnataka

8 registrations under this company
  • Rohan Ekanta Phase 1 PRM/KA/RERA/1251/446/PR/200423/005890 · approved 20 Apr 2023
  • Rohan Ekanta Phase 2 PRM/KA/RERA/1251/446/PR/200423/005887 · approved 20 Apr 2023
  • Rohan Upavan - Phase 2 PRM/KA/RERA/1251/309/PR/190517/002553 · approved 17 May 2019
  • Rohan Upavan - Phase 3 PRM/KA/RERA/1251/309/PR/190517/002554 · approved 17 May 2019
  • Rohan Upavan - Phase 4 PRM/KA/RERA/1251/309/PR/190517/002555 · approved 17 May 2019
  • Rohan Upavan - Phase 5 PRM/KA/RERA/1251/309/PR/190517/002556 · approved 17 May 2019
  • Rohan Upavan - Phase 3A PRM/KA/RERA/1251/309/PR/190517/002557 · approved 17 May 2019
  • Rohan Upavan - Phase 1 PRM/KA/RERA/1251/309/PR/180507/001646 · approved 7 May 2018

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹46.6 crBuilding and development ₹153.0 crTotal ₹199.6 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹253.9 cr₹109.6 cr
Q4 2025-26₹272.4 cr₹118.0 cr
Q1 2026-27₹1.8 cr₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station5.46 kmReliable
  • Nearest railway station3.01 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km8Caveat
  • Nearest lake / water body (≥2 ha)1.09 kmCaveat

Hospitals

  • Nearest hospital1.33 kmCaveat

Schools

  • Schools in pincode 560087 (UDISE+ census)55Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km1Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionVarthur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km1Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well33.1 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.97 kmReliable
  • Nearest sewage treatment plant1.66 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)5.15 kmCaveat
  • Nearest commercial-airport runway28.98 kmReliable
  • Distance to runway approach-path proxy28.26 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)6Caveat

ReliableFrom our location report at the builder-entered pin (12.92721, 77.72486), 2026-10-24. Each figure's source and caveat are in the full report.