Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Rohan Akriti Building 2

by ROHAN GRUH NIRMAN LLP · 210 homes · 3.18 acres · Bengaluru South

Delivered on time Completed: the builder filed for completion on 4 Jul 2022, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 4 Jul 2022, by the date it promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
66 homes per acre

Similar projects within 3 km: 77 per acre. 88% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 3 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?12 due so far
75% on time

Of its 13 RERA projects in Bengaluru Urban: 9 delivered on time, 2 late (after the date first promised), 1 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started31 Mar 2018
  2. Approved by RERA16 May 2018
  3. Completion filed4 Jul 2022

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

  4. First promised31 Dec 2022

    The date the builder gave at registration.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2BHK, 2.5BHK, 3BHK
853 sq ft
79 m² carpet on average · 7 m² balcony
210 homes · 100% of the project

Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. The builder filed the carpet area of all homes of a type together, so sizes marked "on average" are that total divided by the number of homes.

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project66
Typical within 3 km (59)77
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project88%
Typical within 3 km (60)54%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.18 acres

12,858 m²

Ground covered by buildings
12% of the land

1,583 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 13 RERA projects of Rohan Builders on the map

Complaints to RERA about its other projects

The company

Registered as
ROHAN GRUH NIRMAN LLP
Type
Partnership Firm
PAN
AAPFR6652L

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹30.5 cr
Construction
₹80.0 cr
Total project cost
₹110.5 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.58 kmReliable
  • Nearest railway station5.94 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km13Caveat
  • Nearest lake / water body (≥2 ha)0.84 kmCaveat

Hospitals

  • Nearest hospital1.25 kmCaveat

Schools

  • Schools in pincode 560061 (UDISE+ census)55Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionThalaghattapura PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)29 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well8.2 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)9.13 kmReliable
  • Nearest sewage treatment plant2.17 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)14.16 kmCaveat
  • Nearest commercial-airport runway36.98 kmReliable
  • Distance to runway approach-path proxy32.79 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.89017, 77.53805), 2026-10-24. Each figure's source and caveat are in the full report.