RERA project · Residential/Group Housing
Renaissance Nature Walk Phase III (Building 04,Building 09 and Building 10)
by RENAISSANCE HOLDINGS AND DEVELOPERS PVT LTD · 61 homes · 2.80 acres · 3 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 17 Aug 2020, 17 days after the date it first promised.
At a glance
The builder filed for completion on 17 Aug 2020, 17 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 82 per acre. 39% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 7 RERA projects in Bengaluru Urban: 2 delivered on time, 5 late (after the date first promised).
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started3 Dec 2016
- Approved by RERA14 Oct 2017
- Completion filed17 Aug 2020
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 2,689 sq ft14 homes249.8 m²
- 2,679 sq ft13 homes248.9 m²
- 2,667 sq ft7 homes247.8 m²
- 2,676 sq ft6 homes248.6 m²
- and 21 homes in other sizes
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Building 4: 10 homes · Building 9: 29 homes · Building 10: 22 homes
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 2.80 acres
- Ground covered by buildings
- 61% of the land
11,347 m²
6,923 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 7 RERA projects of Renaissance Holdings and Developers Private Limited on the map
The company
- Registered as
- RENAISSANCE HOLDINGS AND DEVELOPERS PVT LTD
- Type
- Company
- Company number
- U07010KA1994PTC016339
- PAN
- AAACR6804J
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171014/000162 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Mismatch in land /boundary - not in accordance with Revenue records and conversion order . Deviation from the sanctioned plan -selling of 5mtr setback land against the clause 8 of snaction plan 22 Sep 2021 · Under Enquiry Authority Fullbench
- Builder violating the Sanction Plan Setback Areas 22 Sep 2021 · Under Enquiry Authority Fullbench
- BUILDER VIOLATION OF SANCTION PLAN And ILLEGALLY SELLING SETBACK LAND 22 Sep 2021 · Under Enquiry Authority Fullbench
Documents
52 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹4.8 cr
- Construction
- ₹59.9 cr
- Total project cost
- ₹64.7 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station2.09 kmReliable
- Nearest railway station4.71 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km3Caveat
- Nearest lake / water body (≥2 ha)0.71 kmCaveat
Hospitals
- Nearest hospital0.7 kmCaveat
Schools
- Schools in pincode 560036 (UDISE+ census)89Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km7Caveat
- Median pupil-teacher ratio, schools within 1 km19.8 :1Caveat
- Schools with library + playground + ICT lab (1 km)5Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionK.R. Puram PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km4Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)8.43 kmReliable
- Nearest sewage treatment plant1.29 kmCaveat
- Industrial zones within 1 km1Caveat
- Nearest airfield runway (any, incl. military)7.1 kmCaveat
- Nearest commercial-airport runway20.24 kmReliable
- Distance to runway approach-path proxy19.68 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat
ReliableFrom our location report at the builder-entered pin (13.00638, 77.71846), 2026-10-24. Each figure's source and caveat are in the full report.