Reliaable Prime City PHASE 1
by RD Buildtech and Developers (Karnataka) Private Limited · 8.91 acres · Anekal
Past due, no completion filed Past its deadline of 30 Sep 2024, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Sep 2024, and no completion is filed.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project. 6 more about the builder's other projects.
The RERA page doesn't say.
Of its 9 RERA projects in Bengaluru Urban: 0 delivered on time, 9 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started15 Dec 2019
- Approved by RERA20 Dec 2019
- First promised31 Dec 2023
The date the builder gave at registration.
- Deadline (extended)30 Sep 2024
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 8.91 acres
- Plot area (the sites)
- 54% of the land
36,068 m²
19,392 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 9 RERA projects of RD Buildtech and Developers (Karnataka) Pvt ltd on the map
Complaints to RERA about its other projects
- RELIAABLE DOLLAR COLLONY Phase 2B 2 complaints
- Reliaable Residenza Phase 1 2 complaints
- RELIAABLE DOLLAR COLLONY 1 complaint
- Reliaable Prime City Phase 1A 1 complaint
The company
- Registered as
- RD Buildtech and Developers (Karnataka) Private Limited
- Type
- Company
- Company number
- U70102KA2011PTC057207
- PAN
- AAFCR1773F
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/191220/003094 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- cancellation of plot and refund 8 Mar 2021 · Disposed Authority Bench4
- Did not receive refund for Reliaable plot 196 cancellation 20 Oct 2021 · Disposed Authority Bench5
- All the proofs are attached as email, As per token advance(2 Lak) refund agreement if they failed to provide legal document they have to return whole amount (2Lak) 13 Aug 2022 · Disposed Authority Bench4
- Refund payment pending from builder after cancelling the booking and allotment of plot no 121 and as committed by the builder. 7 Oct 2022 · Disposed Authority Bench4
Documents
64 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹45.0 cr
- Construction
- ₹12.5 cr
- Total project cost
- ₹57.5 cr
CaveatCost as certified by the builder's chartered accountant at registration.