RERA project · Residential/Group Housing
RAJA RITZ AVENUE - PHASE 1
by RAJA HOUSING LIMITED · 220 homes · 3.50 acres · 5 towers · Bengaluru East
Delivered late Completed: the builder filed for completion on 30 Mar 2026, 1,884 days after the date it first promised.
At a glance
The builder filed for completion on 30 Mar 2026, 1,884 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 46% of the land is left open.
Complaints to RERA about this project. 12 more about the builder's other projects.
The RERA page doesn't say.
Of its 7 RERA projects in Bengaluru Urban: 1 delivered on time, 2 late (after the date first promised), 2 past due with no completion filed, 2 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started1 Aug 2017
- Approved by RERA28 Oct 2017
- First promised31 Jan 2021
The date the builder gave at registration.
- Completion filed30 Mar 2026
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.
Towers
Block 5: 50 homes, 1 basement · block 6: 50 homes, 1 basement · block 7: 40 homes, 1 basement · block 8: 40 homes, 1 basement · block 9: 40 homes, 1 basement
Amenities
- Electricity
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.50 acres
- Ground covered by buildings
- 54% of the land
14,144 m²
7,600 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 7 RERA projects of RAJA HOUSING LIMITED on the map
Complaints to RERA about its other projects
- RAJA RITZ AVENUE - PHASE II 12 complaints
The company
- Registered as
- RAJA HOUSING LIMITED
- Type
- Company
- PAN
- AAACR9798M
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171028/001242 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Project delayed and interest not paid by builder 11 Nov 2021 · Disposed Authority Bench4
- Possession delayed and not paying compensation 10 Dec 2021 · Disposed Authority Bench6
- Project delayed, builder is not responding and not paying compensation for the delay posession 7 Feb 2022 · Disposed Authority Bench6
- Delay in Delivery of Flat and deliberate delay in completion of project 9 Feb 2022 · Disposed Authority Bench6
- Possession delayed, not paying compensation and no proper communication from builder 15 Feb 2022 · Disposed Authority Bench6
- My property is not handed over by RERA pocession date 15 Feb 2022 · Disposed Authority Bench6
- Possession delayed and not paying compensation 15 Feb 2022 · Disposed Authority Bench6
- Rera date expired, possession delayed and compensation not paid 18 Feb 2022 · Disposed Authority Bench6
- Possession date expired by 6 plus months and Not following agreed compensation term as per agreement. 21 Mar 2022 · Disposed Authority Bench6
- Builder wrongfully claiming handover completed without OC, registration of flat, without electricity, water to avoid paying right compensation amount 22 Mar 2022 · Disposed Authority Bench6
- Project delayed - Promoter is not paying monthly compensation 28 Mar 2022 · Disposed Authority Bench6
- Possession Delayed and compensation not paid 28 Mar 2022 · Disposed Authority Bench6
- Denial of payment of monthly compensation & complete handover of apartment 28 Mar 2022 · Disposed Authority Bench6
- Delayed possession and compensation not paid 30 Apr 2022 · Disposed Authority Bench4
- Delay in possession/ handing over 20 May 2022 · Disposed Authority Bench6
- Delayed possession by 17 months. No clarity on compensation 20 May 2022 · Disposed Authority Bench6
- Delayed Possession, Continuous Delays and Fake promises, No Compensation 20 May 2022 · Disposed Authority Bench6
- Possession delayed and not paying compensation. Not updating progress correctly in RERA website. 1 Jun 2022 · Disposed Authority Bench6
- Possession Delayed and not paying compensation 3 Jun 2022 · Disposed Authority Bench6
- Delay in Handover of flat 1.5 year and Non payment of compensation for delay 22 Jun 2022 · Disposed Authority Bench6
- Delay in Possession, No compensation, No proper Communication and Not following RERA/Agreement Guidelines 24 Jun 2022 · Disposed Authority Bench6
- Delay in Handover 11 Jul 2022 · Disposed Authority Bench6
- Delay in handover and no clarity on compensation for delay 20 Jul 2022 · Disposed Authority Bench6
- Delayed Project Delivery and Manipulating on Compensation 20 Jul 2022 · Disposed Authority Bench6
- Possession delayed and not paying compensation 11 Aug 2022 · Disposed Authority Bench5
- DELAYED HANDOVER and DENYING COMPENSATION 16 Aug 2022 · Disposed Authority Bench6
- compensation not received from the Expiry date 18 Aug 2022 · Disposed Authority Bench6
- delay in possession and no clarity in delay compensation calculation 20 Dec 2022 · Disposed Authority Bench6
- Builder Not Rectifying Water Seepage Problem 7 Oct 2024 · Disposed Authority Fullbench
- Complaint under Section 31 against the Builder for unauthorized deviation from the sanctioned layout plan under Section 14 of the RERA Act 1 Jun 2026 · Posted For Orders Authority Fullbench
- Complaint against Raja Housing Limited for unauthorized master plan deviations, security violations, and illegal allocation of common space rights in Raja Ritz Avenue 13 Oct 2026 · Under Enquiry Ao
Documents
95 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹97.5 lakh
- Construction
- ₹72.0 cr
- Total project cost
- ₹73.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.