Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

RAINTREE

by Lewis Infrastructure and Projects · 8 homes · 0.14 acres · 1 tower · Bengaluru North

Delivered late Completed: the builder filed for completion on 19 Aug 2020, 180 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 19 Aug 2020, 180 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
58 homes per acre

Similar projects across the city: 76 per acre. 35% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?7 due so far
14% on time

Of its 9 RERA projects in Bengaluru Urban: 1 delivered on time, 4 late (after the date first promised), 2 past due with no completion filed, 2 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started21 Feb 2018
  2. Approved by RERA2 Jun 2018
  3. Completion filed19 Aug 2020

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3BHK
1,987 sq ft
185 m² carpet · sizes 1,785–3,233 sq ft (2 at this size)
72 m² land share · 2 parking spaces
8 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Raintree3 floors

Raintree: 8 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project58
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project35%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.14 acres

557 m²

Ground covered by buildings
65% of the land

362 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 9 RERA projects of LEWIS INFRASTRUCTURE AND PROJECTS on the map

The company

Registered as
Lewis Infrastructure and Projects
Type
Partnership Firm
PAN
AAMFN4665N

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹3.4 cr
Construction
₹4.5 cr
Total project cost
₹4.5 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.