Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

RAAGA BY BHAVISHA HOMES

by Bhavisha Properties · 76 homes · 1.37 acres · 1 tower · Anekal

Past due, no completion filed Past its deadline of 31 Dec 2025, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 31 Dec 2025, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
55 homes per acre

Similar projects within 3 km: 70 per acre. 56% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 3 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?23 due so far
4% on time

Of its 27 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 21 past due with no completion filed, 4 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started17 Jun 2024
  2. Approved by RERA26 Sep 2024
  3. Deadline31 Dec 2025

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3 BHK
1,166 sq ft
108 m² carpet · sizes 1,165–1,199 sq ft (28 at this size)
74 m² land share · 29 m² balcony/terrace · 1 parking space
68 homes · 89% of the project
2 BHK
865 sq ft
80 m² carpet
56 m² land share · 22 m² balcony/terrace · 1 parking space
8 homes · 11% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Raaga By Bhavisha Homes3 floors

Raaga By Bhavisha Homes: 76 homes, 15 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project55
Typical within 3 km (85)70
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project56%
Typical within 3 km (87)60%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.37 acres

5,561 m²

Ground covered by buildings
44% of the land

2,435 m²

Floor-area ratio
1.74

Floors built per unit of land: 1.74 m² of floors for each m² of land.

Parking
1.00 per home

76 covered, 0 open

Built-up area, all floors
1,35,216 sq ft

12,562 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 27 RERA projects of Bhavisha on the map

Complaints to RERA about its other projects

The company

Registered as
Bhavisha Properties
Type
Proprietorship

Its other registrations on RERA Karnataka

15 registrations under this company
  • BILVA PHASE-II BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/280325/007639 · approved 28 Mar 2025
  • MEADOWS PHASE-2 BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/300924/007099 · approved 30 Sep 2024
  • CASA LIFE BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/220424/006822 · approved 22 Apr 2024
  • Bhavisha Bilva PRM/KA/RERA/1251/446/PR/151223/006481 · approved 15 Dec 2023
  • Bhavisha Avighna PRM/KA/RERA/1251/446/PR/271123/006437 · approved 27 Nov 2023
  • Bhavisha Bentley goldberg phase 2 PRM/KA/RERA/1251/308/PR/030223/005682 · approved 3 Feb 2023
  • Bhavisha Bentley Goldberg Phase-1 PRM/KA/RERA/1251/308/PR/010722/005033 · approved 1 Jul 2022
  • Bhavisha Meadows PRM/KA/RERA/1251/308/PR/300622/005027 · approved 30 Jun 2022
  • Bavisha Greystone PRM/KA/RERA/1251/308/PR/220104/004625 · approved 4 Jan 2022
  • Bavisha Greenwoods PRM/KA/RERA/1251/308/PR/211130/004557 · approved 30 Nov 2021
  • BHAVISHA BENTLEY GREENS PHASE 2 PRM/KA/RERA/1251/308/PR/210928/004315 · approved 28 Sep 2021
  • Bavisha Gardeniaa Phase 3 PRM/KA/RERA/1251/308/PR/210422/004144 · approved 22 Apr 2021
  • Bavisha Gardeniaa Phase 2 PRM/KA/RERA/1251/308/PR/210401/004091 · approved 1 Apr 2021
  • Bhavisha Bentley Greens PRM/KA/RERA/1251/308/PR/200827/003572 · approved 27 Aug 2020
  • Bavisha Gardeniaa PRM/KA/RERA/1251/308/PR/200817/003549 · approved 17 Aug 2020

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹4.0 crBuilding and development ₹45.0 crTotal ₹49.0 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station10.02 kmReliable
  • Nearest railway station8.21 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.57 kmCaveat

Hospitals

  • Nearest hospital0.17 kmCaveat

Schools

  • Schools in pincode 562125 (UDISE+ census)91Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
  • Median pupil-teacher ratio, schools within 1 km18.3 :1Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSarjapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)13.38 kmReliable
  • Nearest sewage treatment plant5.6 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)13.18 kmCaveat
  • Nearest commercial-airport runway36.12 kmReliable
  • Distance to runway approach-path proxy34.45 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.86514, 77.76805), 2026-10-24. Each figure's source and caveat are in the full report.