Upcoming Under construction, due Dec 2027. 96% built with 79% of the time used. 98% of homes booked.
At a glance
Due 31 Dec 2027. 79% of the time from RERA approval to the deadline has passed.
121 of 123 homes, as the builder reported for Q3 2025-26.
Similar projects within 3 km: 74 per acre. 49% of the land is left open.
Complaints to RERA about this project. 98 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 37 RERA projects in Bengaluru Urban: 2 delivered on time, 8 late (after the date first promised), 8 past due with no completion filed, 17 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Oct 2020
- Approved by RERA1 Jun 2022
- Today24 Oct 2026
79% of the time to the deadline has passed.
- Deadline31 Dec 2027
The date it must be complete by.
- If it slips like a typical project1 Oct 2028
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 2 × 3BHK.
Booked, by type
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Wing D: 123 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.33 acres
- Ground covered by buildings
- 51% of the land
1,321 m²
673 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 37 RERA projects of Puravankara on the map
Complaints to RERA about its other projects
98 complaints across 17 projects. The most complained about:
- Provident Park Square Phase - 1 18 complaints
- Provident Park Square 4 16 complaints
- Purva Palmbeach 14 complaints
- Provident Park Square Phase 3 (Towers 5A and 5B) 8 complaints
- Purva Park Hill (Wing C) 7 complaints
Show all 17 projects
- Purva Sunflower 6 complaints
- Purva Westend Phase 1 5 complaints
- Provident Woodfield 5 complaints
- Purva Atmosphere 5 complaints
- Provident Park Square Phase 2 3 complaints
- Purva Oakshire 3 complaints
- Provident Park Square 5 2 complaints
- Sound of Water Phase 1 by Puravankara 2 complaints
- PURVA PALMBEACH 1 complaint
- Purva Coronation Square 1 complaint
- Purva Zenium 2 1 complaint
- Purva Zenium 1 1 complaint
The company
- Registered as
- Puravankara Limited
- Type
- Company
- Company number
- L45200KA1986PLC051571
- PAN
- AAACP2550R
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/220601/004949 · Approved
- Building plan approvedLocal Planing Authority
- Litigation on the landNot stated
- Litigation on the projectNone declared in the Q3 2025-26 update
Complaints to RERA about this project
- delay in delivery of apartment as per agreed date , so need compensation and actual handover date 15 Oct 2025 · Disposed Authority Bench4
- Compensation for delay in hand over/Possession 7 Feb 2026 · Posted For Orders Authority Bench4
- Delivery date was 30thSep 2025 latest, financial compensation (Interest on amount paid to Purvankara till now) needed for delay 10 Feb 2026 · Posted For Orders Authority Bench4
- Delay in Possession – Claim for Interest – Purva Park Hill 18 Feb 2026 · Posted For Orders Authority Bench4
- Ongoing Delay in possession since grace period got over on 1stSep2025 causing immense financial hardship and agony 18 Feb 2026 · Posted For Orders Authority Bench4
- Deserve rental amount compensation - Ongoing Delay in possession (grace period till 1stSep2025) causing finance problem because of EMI and monthly rent BOTH 18 Feb 2026 · Disposed Ao
- Apartment not delivered yet 18 Feb 2026 · Disposed Ao
- delay in delivery of apartment as per agreed date , so need compensation and actual handover date 5 Mar 2026 · Disposed Authority Bench4
- Non-Compliance of Scheduled Delivery Date 4 May 2026 · Posted For Orders Authority Bench4
- Immediate possession of flat Purva Park Hill D 604 and compensation for the delayed possession 11 May 2026 · Under Enquiry Authority Bench4
- Ongoing Delay in possession since grace period got over on 1stSep2025 causing immense financial hardship and agony 25 May 2026 · Under Enquiry Authority Bench4
- Immediate possession of flat Purva Park Hill D 604 and compensation for the delayed possession 27 May 2026 · Disposed Ao
- Delay Period intrest 29 May 2026 · Under Enquiry Authority Bench4
Documents
159 files on the RERA page: Approved plan ↗, Commencement certificate ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹24.2 cr
- Construction
- ₹62.8 cr
- Total project cost
- ₹87.0 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹1.3 cr | ₹88.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station1.58 kmReliable
- Nearest railway station9.46 kmReliable
- Bus stops within 500 m3Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km4Caveat
- Nearest lake / water body (≥2 ha)1.78 kmCaveat
Hospitals
- Nearest hospital2.67 kmCaveat
Schools
- Schools in pincode 560062 (UDISE+ census)66Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km1Caveat
- Schools with library + playground + ICT lab (1 km)1Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionThalaghattapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well8.2 m below groundCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km1Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)6.08 kmReliable
- Nearest sewage treatment plant5.8 kmCaveat
- Industrial zones within 1 km1Caveat
- Nearest airfield runway (any, incl. military)15.98 kmCaveat
- Nearest commercial-airport runway40.37 kmReliable
- Distance to runway approach-path proxy36.51 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat
ReliableFrom our location report at the builder-entered pin (12.85441, 77.54248), 2026-10-24. Each figure's source and caveat are in the full report.