Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Purva Park Hill (Wing B)

by Puravankara Limited · 123 homes · 0.44 acres · 1 tower · Bengaluru South

Upcoming Under construction, due Dec 2027. 80% built with 79% of the time used. 99% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
80% built

Due 31 Dec 2027. 79% of the time from RERA approval to the deadline has passed.

Built80%
Time used79%
How much is sold?1 left
99% booked

122 of 123 homes, as the builder reported for Q3 2025-26.

How crowded is it?More crowded
282 homes per acre

Similar projects within 3 km: 74 per acre. 49% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 111 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?18 due so far
11% on time

Of its 37 RERA projects in Bengaluru Urban: 2 delivered on time, 8 late (after the date first promised), 8 past due with no completion filed, 17 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Oct 2020
  2. Approved by RERA1 Jun 2022
  3. Today24 Oct 2026

    79% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2680%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

122 booked1 leftQ3 2025-26

Still available: 1 × 3BHK.

Booked, by type

2BHK16 of 16
3BHK106 of 107

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK
1,168 sq ft
108 m² carpet · sizes 1,051–1,168 sq ft (82 at this size)
0 m² land share · 1 parking space
107 homes · 87% of the project
2BHK
808 sq ft
75 m² carpet
0 m² land share · 1 parking space
16 homes · 13% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Wing B20 floors

Wing B: 123 homes, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project282
Typical within 3 km (50)74
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project49%
Typical within 3 km (50)63%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.44 acres

1,762 m²

Ground covered by buildings
51% of the land

893 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 37 RERA projects of Puravankara on the map

Complaints to RERA about its other projects

111 complaints across 18 projects. The most complained about:

Show all 18 projects
  • Purva Park Hill (Wing C) 7 complaints
  • Purva Sunflower 6 complaints
  • Purva Westend Phase 1 5 complaints
  • Provident Woodfield 5 complaints
  • Purva Atmosphere 5 complaints
  • Provident Park Square Phase 2 3 complaints
  • Purva Oakshire 3 complaints
  • Provident Park Square 5 2 complaints
  • Sound of Water Phase 1 by Puravankara 2 complaints
  • PURVA PALMBEACH 1 complaint
  • Purva Coronation Square 1 complaint
  • Purva Zenium 2 1 complaint
  • Purva Zenium 1 1 complaint

The company

Registered as
Puravankara Limited
Type
Company
Company number
L45200KA1986PLC051571

CIN or LLPIN, from the Registrar of Companies.

PAN
AAACP2550R

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹24.0 cr
Construction
₹62.3 cr
Total project cost
₹86.4 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹6.0 cr₹4.2 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.6 kmReliable
  • Nearest railway station9.48 kmReliable
  • Bus stops within 500 m3Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km3Caveat
  • Nearest lake / water body (≥2 ha)1.8 kmCaveat

Hospitals

  • Nearest hospital2.67 kmCaveat

Schools

  • Schools in pincode 560062 (UDISE+ census)66Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km1Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionThalaghattapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well8.2 m below groundCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.06 kmReliable
  • Nearest sewage treatment plant5.79 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)15.96 kmCaveat
  • Nearest commercial-airport runway40.36 kmReliable
  • Distance to runway approach-path proxy36.51 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.85441, 77.54273), 2026-10-24. Each figure's source and caveat are in the full report.