RERA project · Mixed Development
PURSUITOFARADICALRHAPSODYPHASE1
by Total Environment Habitat Private Limited · 552 homes · 14.09 acres · 5 towers · Bengaluru East
Upcoming Under construction, due Apr 2027, after an extension. 75% built with 95% of the time used. 98% of homes booked.
At a glance
Due 30 Apr 2027. 95% of the time from RERA approval to the deadline has passed.
539 of 552 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 84 per acre. 50% of the land is left open.
Complaints to RERA about this project. 5 more about the builder's other projects.
The builder declares litigation on the land or the project.
Of its 22 RERA projects in Bengaluru Urban: 1 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 13 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started19 Oct 2015
- Approved by RERA14 Oct 2017
- First promised31 Jul 2024
The date the builder gave at registration.
- Today24 Oct 2026
95% of the time to the deadline has passed.
- Deadline (extended)30 Apr 2027
The date it must be complete by.
- If it slips like a typical project30 Jan 2028
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 4 × 3 BHK, 2 × 2 BHK, 1 × 4 BHK, 6 × 5 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower 01: 114 homes, 2 basements · Tower 02: 130 homes, 2 basements · Tower 03: 130 homes, 2 basements · Tower 04: 130 homes, 2 basements · Villas: 48 homes
Amenities
- Electricity
- Club House
- Community Hall
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 14.09 acres
- Ground covered by buildings
- 50% of the land
57,002 m²
28,356 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active mixed development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 22 RERA projects of Total Environment on the map
Complaints to RERA about its other projects
- PURSUIT OF A RADICAL RHAPSODY PHASE 2 5 complaints
The company
- Registered as
- Total Environment Habitat Private Limited
- Type
- Company
- Company number
- U45201KA2010PTC054651
- PAN
- AADCT5683N
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171014/000433 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectDeclared in the Q2 2026-27 update
Complaints to RERA about this project
- Delay in completion 18 Sep 2021 · Disposed Ao
- VOILATION OF RULES AND REGULATIONS STIPULATED UNDER SECTION 131 OF THE REAL ESTATE REGULATORY AUTHORITY ACT - 2016 5 Oct 2021 · Disposed Authority Fullbench
- Need Compensation for Delayed possession 26 Aug 2024 · Disposed Authority Bench4
- Delayed delivery and arbitrary revision in schedule of delivery of the unit 10 Sep 2024 · Disposed Authority Bench4
- Complaint seeking Compensation for Delayed Possession 25 Sep 2024 · Posted For Orders Authority Bench4
- Delay in handover of possession 1 Oct 2024 · Disposed Authority Bench5
- Expiry of Delivery Date, Delay in Handover and Interest on Delay Period 18 Oct 2024 · Disposed Authority Fullbench
- Compensation for delays and delays in execution of changes 2 Dec 2024 · Disposed Authority Bench4
- Delay in possession/handover of the unit #3244 17 Dec 2024 · Disposed Authority Bench4
- Delay in handover 8 Mar 2025 · Disposed Authority Bench4
- Unfair Withholding of Contractual Commitments and Arbitrary Revisions to Compensation and Rent Support 13 May 2025 · Disposed Authority Fullbench
- INTEREST ON DELAY PERIOD 15 Jul 2025 · Posted For Orders Authority Bench4
- Delivery delayed 15 Jul 2025 · Posted For Orders Authority Bench4
- Delay in Possession and Denied Compensation 21 Aug 2025 · Posted For Orders Authority Bench4
- delay in hand over of the flat hence compensation for the delay and execution and registration of the sale deed 29 Aug 2025 · Disposed Authority Bench4
- Delay in possession of the said unit #3291 29 Aug 2025 · Disposed Authority Bench4
- Breach of contract on Settlement Agreement signed for payment of penalty for delay in possession 10 Aug 2026 · Under Enquiry Authority Bench4
- Delay in completion and lawful handover of Unit No. 3284 in Pursuit of a Radical Rhapsody Phase 1 and non-payment of contractual/statutory delay compensation by the Respondent. 27 Aug 2026 · Under Enquiry Authority Bench4
- Non-payment of compensation due under Settlement Agreement dated 09-Feb-2026 by the Respondent, Total Environment Habitat Private Limited 2 Sep 2026 · Under Enquiry Authority Bench4
- Non-compliance with the executed Settlement Agreement – non-payment of agreed delay compensation 11 Sep 2026 · Under Enquiry Authority Bench4
- Complaint for Delay in Possession, Non-Disbursement of Delay Interest, and Non-Fulfillment of Contractual Commitments for Villa #19 in Total Environment Project "Pursuit of a radical rhapsody" 12 Oct 2026 · Scrutiny Completed
Documents
116 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹293.2 cr
- Construction
- ₹945.8 cr
- Total project cost
- ₹1920.1 cr
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹11.6 cr | ₹11.6 cr |
| Q4 2025-26 | ₹14.3 cr | ₹12.9 cr |
| Q1 2026-27 | ₹23.9 cr | ₹23.9 cr |
| Q2 2026-27 | ₹5.8 cr | ₹5.8 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station0.97 kmReliable
- Nearest railway station4.56 kmReliable
- Bus stops within 500 m2Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km11Caveat
- Nearest lake / water body (≥2 ha)0.33 kmCaveat
Hospitals
- Nearest hospital0.92 kmCaveat
Schools
- Schools in pincode 560048 (UDISE+ census)39Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km9Caveat
- Median pupil-teacher ratio, schools within 1 km30 :1Caveat
- Schools with library + playground + ICT lab (1 km)6Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionMahadevapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km2Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)yesCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)10.43 kmReliable
- Nearest sewage treatment plant1.12 kmCaveat
- Industrial zones within 1 km9Caveat
- Nearest airfield runway (any, incl. military)5.6 kmCaveat
- Nearest commercial-airport runway22.27 kmReliable
- Distance to runway approach-path proxy21.67 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.98793, 77.72023), 2026-10-24. Each figure's source and caveat are in the full report.