Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

PSR VANASREE PHASE-II

by M/s PSR BUILDERS AND DEVELOPERS · 224 homes · 2.39 acres · 2 towers · Bengaluru East

Upcoming Under construction, due Dec 2027. 44% built with 61% of the time used. 26% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
44% built

Due 31 Dec 2027. 61% of the time from RERA approval to the deadline has passed.

Built44%
Time used61%
How much is sold?166 left
26% booked

58 of 224 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
94 homes per acre

Similar projects within 3 km: 68 per acre. 81% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 4 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?Too early to tell
No deliveries yet

None of its 3 RERA projects in Bengaluru Urban has reached its deadline yet.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 May 2024
  2. Approved by RERA26 Dec 2024
  3. Today24 Oct 2026

    61% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2620%
Q4 2025-2628%
Q1 2026-2733%
Q2 2026-2744%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower 244%
Tower344%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

58 booked166 leftQ2 2026-27

Still available: 71 × 2 BHK, 95 × 3 BHK.

Booked, by type

2 BHK27 of 98
3 BHK31 of 126

Booked, each quarter

Q3 2025-2635 of 224
Q4 2025-2642 of 224
Q1 2026-2750 of 224
Q2 2026-2758 of 224

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
928 sq ft
86 m² carpet · sizes 872–972 sq ft (42 at this size)
47 m² land share · 14 m² balcony/terrace · 1 parking space
126 homes · 56% of the project
2 BHK
750 sq ft
70 m² carpet · sizes 719–767 sq ft (28 at this size)
38 m² land share · 11 m² balcony/terrace · 1 parking space
98 homes · 44% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower 213 floors
Tower313 floors

Tower 2: 112 homes, 44 m tall, 1 basement · Tower3: 112 homes, 448 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project94
Typical within 3 km (87)68
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project81%
Typical within 3 km (87)69%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.39 acres

9,691 m²

Ground covered by buildings
19% of the land

1,858 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.10 per home

246 covered, 0 open

Built-up area, all floors
2,80,712 sq ft

26,079 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 3 RERA projects of M/s PSR BUILDERS AND DEVELOPERS on the map

Complaints to RERA about its other projects

The company

Registered as
M/s PSR BUILDERS AND DEVELOPERS
Type
Proprietorship
Website
www.psrbuildersanddevelopers.com

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹47.8 crBuilding and development ₹96.5 crTotal ₹144.3 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹6.8 cr₹5.9 cr
Q4 2025-26₹17.4 cr₹15.3 cr
Q1 2026-27₹46.7 cr₹20.8 cr
Q2 2026-27₹58.0 cr₹11.7 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station6.1 kmReliable
  • Nearest railway station1.99 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km8Caveat
  • Nearest lake / water body (≥2 ha)0.68 kmCaveat

Hospitals

  • Nearest hospital1.57 kmCaveat

Schools

  • Schools in pincode 560035 (UDISE+ census)45Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
  • Schools with library + playground + ICT lab (1 km)2Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionVarthur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.53 kmReliable
  • Nearest sewage treatment plant3.51 kmCaveat
  • Industrial zones within 1 km3Caveat
  • Nearest airfield runway (any, incl. military)7.33 kmCaveat
  • Nearest commercial-airport runway33.15 kmReliable
  • Distance to runway approach-path proxy32.61 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (12.88962, 77.70855), 2026-10-24. Each figure's source and caveat are in the full report.