RERA project · Plotted Development
PSN Misty Woods
by P S N Developers · 117 plots · 7.12 acres · Bengaluru South
Upcoming Under construction, due Dec 2027. 64% built with 53% of the time used.
At a glance
Due 31 Dec 2027. 53% of the time from RERA approval to the deadline has passed.
The builder has not filed bookings on RERA.
Similar projects across the city: 16 per acre. 49% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started29 Apr 2025
- Approved by RERA17 Jun 2025
- Today24 Oct 2026
53% of the time to the deadline has passed.
- Deadline31 Dec 2027
The date it must be complete by.
- If it slips like a typical project1 Oct 2028
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
This project's RERA page has no flat-by-flat list, so these are the builder's summary figures, exactly as filed. Builders often give the area of all plots of a size together there: a figure marked "in all" covers every one of them, not one plot.
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Plots per acre
Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 7.12 acres
- Plot area (the sites)
- 51% of the land
- Roads
- 8,709 m²
- Parks and open spaces
- 5,042 m²
- Civic amenity sites
- 293 m²
28,833 m²
14,789 m²
Sites kept for public uses such as a school or a health centre.
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- P S N Developers
- Type
- Partnership Firm
- PAN
- ABEFP1901G
- GSTIN
- 29ABEFP1901G1ZF
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/170625/007841 · Approved
- Building plan approvedBDA - Bangalore Development Authority · BDA/TPM/PRL-18/3596/2024-25 · 29 Mar 2025
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBoreWell,Local Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
148 files on the RERA page.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹42.1 lakh | ₹0.0 lakh |
| Q4 2025-26 | ₹2.0 cr | ₹1.3 cr |
| Q1 2026-27 | ₹10.4 cr | ₹4.3 cr |
| Q2 2026-27 | ₹2.2 cr | ₹4.4 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.