Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

pristine symphony

by pristine builders · 44 homes · 0.36 acres · 1 tower · Bengaluru South

Delivered late Completed: the builder filed for completion on 28 Nov 2021, 300 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 28 Nov 2021, 300 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
121 homes per acre

Similar projects across the city: 76 per acre. 45% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?2 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 1 past due with no completion filed.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started3 May 2017
  2. Approved by RERA14 Dec 2017
  3. First promised1 Feb 2021

    The date the builder gave at registration.

  4. Completion filed28 Nov 2021

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2 BHK
  • 551 sq ft4 homes51.2 m²
  • 553 sq ft4 homes51.4 m²
  • 579 sq ft4 homes53.8 m²
  • 587 sq ft4 homes54.5 m²
  • and 20 homes in other sizes
Typically 32 m² land share · 17 m² balcony/terrace · 1 parking space
36 homes · 82% of the project
1 BHK
  • 409 sq ft4 homes38.0 m²
  • 426 sq ft4 homes39.6 m²
Typically 21 m² land share · 11 m² balcony/terrace
8 homes · 18% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Pristine Symphony4 floors

Pristine Symphony: 44 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project121
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project45%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.36 acres

1,467 m²

Ground covered by buildings
55% of the land

807 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of pristine builders on the map

The company

Registered as
pristine builders
Type
Partnership Firm
PAN
AAOFP3717D

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Construction
₹3.6 cr
Total project cost
₹4.0 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.