Prestige Lakeside Habitat
by Prestige Habitat Ventures · 3,697 homes · 99.17 acres · 12 towers · Bengaluru East
Delivered on time Completed: the builder filed for completion on 28 Dec 2018, by the date it promised.
At a glance
The builder filed for completion on 28 Dec 2018, by the date it promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 81% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 73 RERA projects in Bengaluru Urban: 14 delivered on time, 34 late (after the date first promised), 7 past due with no completion filed, 17 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started10 May 2015
- Approved by RERA15 Sep 2017
- Completion filed28 Dec 2018
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Building 1 (Tower1,Tower2,Tower3): 533 homes, 2 basements · Building 2 (Tower 4, Tower5,Tower6): 461 homes, 2 basements · Building 3 (Tower 7,Tower 8): 284 homes, 2 basements · Building 4 (Tower 9,Tower 10,Tower11): 501 homes, 1 basement · Building 5 (Tower 12,Tower13): 238 homes, 2 basements · Building 6 (Tower 14): 119 homes, 2 basements · Building 7 ( Tower 15, Tower16, Tower17): 529 homes, 2 basements · Building 8 (Tower18): 119 homes, 2 basements · Building 9 (Tower19,20): 145 homes, 2 basements · Building10 (Tower21,Tower22): 205 homes, 2 basements · Building 11 (Tower 23,Tower 24): 292 homes, 2 basements · Building 12: 271 homes
Amenities
- Electricity
- Smart Home Automation
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
- Amphitheatre
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 99.17 acres
- Ground covered by buildings
- 19% of the land
4,01,318 m²
76,000 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 73 RERA projects of Prestige Group on the map
The company
- Registered as
- Prestige Habitat Ventures
- Type
- Partnership Firm
- PAN
- AAOFP5729K
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/170915/000176 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Deliberate delay of a ready to move in property, Not honoring promise of two car parks and demanding more money using loopholes, if I am upset by these two & wants to cancel then a threat of penalty 6 Apr 2020 · Disposed Ao
- CAM (Common Area Maintenance) is being charged from the date 16th Aug 2020, while the purchase of the flat was done on Nov-2020 via Assignment Agreement. 23 Nov 2021 · Disposed Authority Bench5
Documents
42 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹1137.6 cr
- Construction
- ₹1872.8 cr
- Total project cost
- ₹3010.4 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.