RERA project · Residential/Group Housing
Plumeria Lifestyle at Brigade Meadows
by Brigade Enterprises Ltd · 412 homes · 3.92 acres · 7 towers · Bengaluru South
Delivered late Completed: the builder filed for completion on 17 Nov 2020, 48 days after the date it first promised.
At a glance
The builder filed for completion on 17 Nov 2020, 48 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 64 per acre. 65% of the land is left open.
Complaints to RERA about this project. 41 more about the builder's other projects.
The RERA page doesn't say.
Of its 55 RERA projects in Bengaluru Urban: 0 delivered on time, 23 late (after the date first promised), 12 past due with no completion filed, 18 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started27 Jul 2018
- Approved by RERA22 Oct 2018
- First promised30 Sep 2020
The date the builder gave at registration.
- Completion filed17 Nov 2020
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
C: 72 homes, 1 basement · D: 72 homes, 2 basements · E: 52 homes, 2 basements · F: 54 homes, 2 basements · G: 54 homes, 2 basements · H: 54 homes, 2 basements · I: 54 homes, 1 basement
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.92 acres
- Ground covered by buildings
- 35% of the land
15,866 m²
5,570 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 55 RERA projects of Brigade Group on the map
Complaints to RERA about its other projects
41 complaints across 19 projects. The most complained about:
- Brigade Panorama 8 complaints
- Brigade Atmosphere- Phase 1 3 complaints
- Brigade Sanctuary 3 complaints
- Brigade Oasis - Phase 2 3 complaints
- Brigade Buena Vista-Phase 2 2 complaints
Show all 19 projects
- Brigade Woods 2 complaints
- Brigade Parkside East 2 complaints
- Brigade 7 Gardens 2 complaints
- Brigade Laguna 2 complaints
- Brigade Parkside North 2 complaints
- Brigade Northridge Neo 2 complaints
- Brigade Oasis - Phase 3 2 complaints
- Brigade Oak Tree Place 2 complaints
- Brigade Lakefront - Crimson 1 complaint
- Plumeria Phase 1 at Brigade Meadows 1 complaint
- Brillio and Commercial at Brigade Valencia 1 complaint
- Brigade Eternia 1 complaint
- BRIGADE KOMARLA HEIGHTS 1 complaint
- Brigade Oasis - Phase 1 1 complaint
The company
- Registered as
- Brigade Enterprises Ltd
- Type
- Company
- Company number
- L85110KA1995PLC019126
- PAN
- AAACB7459F
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/181022/002096 · Approved
- Building plan approvedLocal Planing Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Recovery of delay compensation, rental loss & Property tax amount with Interest for 6 years of delay caused by builder to deliver possession of flat 12 Feb 2021 · Disposed Authority Bench4
- 20000/- rs taken falsely by threatening to not handover house keys and falsely pushed me into the flat stating all the work is done 13 Jan 2022 · Disposed Authority Bench4
- Dear Sir, Regarding return of deposited amount of Rs. 2100000.00 (Rupees Twenty One Lakhs only) towards Flat No. 0537 at Brigade Meadows Plumeria Lifestyle. 29 Jan 2022 · Disposed Authority Bench4
Documents
46 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹11.0 cr
- Construction
- ₹200.0 cr
- Total project cost
- ₹211.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station5.69 kmReliable
- Nearest railway station10.59 kmReliable
- Bus stops within 500 m1Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km4Caveat
- Nearest lake / water body (≥2 ha)1.52 kmCaveat
Hospitals
- Nearest hospital0.12 kmCaveat
Schools
- Schools in pincode 560082 (UDISE+ census)71Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
- Median pupil-teacher ratio, schools within 1 km17.5 :1Caveat
- Schools with library + playground + ICT lab (1 km)3Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionKaggalipura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km1Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)8.81 kmReliable
- Nearest sewage treatment plant8.47 kmCaveat
- Industrial zones within 1 km1Caveat
- Nearest airfield runway (any, incl. military)21.61 kmCaveat
- Nearest commercial-airport runway45.88 kmReliable
- Distance to runway approach-path proxy41.7 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (12.81428, 77.50959), 2026-10-24. Each figure's source and caveat are in the full report.