RERA project · Residential/Group Housing
Pinegrove
by Janapriya Engineers Syndicate Private Limited · 119 homes · 5.17 acres · 1 tower · Bengaluru South
Delivered late Completed: the builder filed for completion on 21 May 2026, 506 days after the date it first promised.
At a glance
The builder filed for completion on 21 May 2026, 506 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 84% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started31 Jul 2017
- Approved by RERA26 Oct 2017
- First promised31 Dec 2024
The date the builder gave at registration.
- Completion filed21 May 2026
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Canary Island: 119 homes, 1 basement
Amenities
- Electricity
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Gas
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.17 acres
- Ground covered by buildings
- 16% of the land
20,916 m²
3,434 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Janapriya Engineers Syndicate Private Limited
- Type
- Company
- Company number
- U45200AP1995PTC020949
- PAN
- AAACE4560A
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171026/000675 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Delay in delivery by more than 2.5 years 1 Mar 2020 · Disposed Authority Bench5
- Delayed project by Janapriya for over 5 years 20 Aug 2020 · Disposed Ao
- Compensation & Delayed Construction 6 Aug 2022 · Disposed Authority
- Incomplete property, delayed timelines, security risks & ignorant behaviour of the builder 16 Dec 2022 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behaviour of the builder 16 Dec 2022 · Disposed Authority Bench5
- Incomplete Property, delayed timelines, security risks & ignorant behaviour of the builder and landowners. 19 Dec 2022 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behavior of the builder 21 Dec 2022 · Disposed Authority Bench5
- Incomplete property, delayed timelines, Security risks 23 Mar 2023 · Disposed Authority Bench5
- Compensation for delay in providing agreed amenities as per agreement 23 Mar 2023 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behaviour of the builder 1 Apr 2023 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behavior of the builder 1 Apr 2023 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behaviour of the builder, Poor Building Quality 1 Apr 2023 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behavior of the builder 1 Apr 2023 · Disposed Authority Bench5
- Incomplete property, delayed timelines, security risks & ignorant behavior of the builder 1 Apr 2023 · Disposed Authority Bench5
- Incomplete propery, delayed, security risks & security risks 3 Apr 2023 · Disposed Authority Bench5
- Incomplete Property, Delayed TImelines, Security risks & Ignorant behavior of builder 30 Jun 2023 · Disposed Authority Bench5
- ncomplete property, delayed timelines, security risks & ignorant behaviour of the builder 30 Jun 2023 · Disposed Authority Bench5
- Pending documents MOD of IDBI and Discharge deed of IDBI 2 Dec 2023 · Disposed Authority Bench5
- Incomplete project, Delay in completion, Amenities not completed, Clubhouse not completed, Security risks 17 Feb 2025 · Disposed Authority Bench5
- Relief sought for completion of amenities and refund of corpus amount 9 Jun 2026 · Under Enquiry Authority Bench5
- Builder has not allotted the Car Parking Space as per Agreement of Sale 11 Jun 2026 · Under Enquiry Authority Bench5
Documents
49 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Construction
- ₹138.0 cr
- Total project cost
- ₹138.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.