RERA project · Residential/Group Housing
PAVANI MIRABILIA PHASE III
by Sai Sravanthi Infra Projects Pvt Ltd · 239 homes · 1.04 acres · 1 tower · Bengaluru East
Upcoming Under construction, due Mar 2031. 2% built with 7% of the time used. 0% of homes booked.
At a glance
Due 3 Mar 2031. 7% of the time from RERA approval to the deadline has passed.
0 of 239 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 80 per acre. 63% of the land is left open.
Complaints to RERA about this project. 3 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 4 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 3 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started6 Mar 2026
- Approved by RERA24 Jun 2026
- Today24 Oct 2026
7% of the time to the deadline has passed.
- Deadline3 Mar 2031
The date it must be complete by.
- If it slips like a typical project3 Dec 2031
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 239 × 3 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 955 sq ft80 homes88.7 m²
- 844 sq ft79 homes78.4 m²
- 1,016 sq ft60 homes94.4 m²
- 958 sq ft20 homes89.0 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower F: 239 homes, 60 m tall, 2 basements
Amenities
- Electricity 890 m²
- Club House 5,104 m²
- Outdoor Sports facility 150 m²
- Indoor Sports facility 240 m²
- Swimming Pool 180 m²
- Gym 60 m²
- Parks 800 m²
- Power Backup
- Water and Sanitation 60 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.04 acres
- Ground covered by buildings
- 37% of the land
- Floor-area ratio
- 4.00
- Parking
- 2.00 per home
- Built-up area, all floors
- 3,50,160 sq ft
4,228 m²
1,565 m²
Floors built per unit of land: 4.00 m² of floors for each m² of land.
239 covered, 0 open
32,531 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 4 RERA projects of Sai Sravanthi Infra Projects Pvt Ltd on the map
Complaints to RERA about its other projects
- PAVANI MIRABILIA PHASE I 3 complaints
The company
- Registered as
- Sai Sravanthi Infra Projects Pvt Ltd
- Type
- Company
- Company number
- U45203TG2008PTC060151
- PAN
- AAPCS0464C
- GSTIN
- 29AAPCS0464C1Z9
- Website
- [email protected]
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- PAVANI MIRABILIA PHASE-II PRM/KA/RERA/1251/446/PR/200224/006641 · approved 20 Feb 2024
- PAVANI MIRABILIA PHASE I PRM/KA/RERA/1251/446/PR/120922/005235 · approved 12 Sep 2022
- Pavani Divine PRM/KA/RERA/1251/446/PR/171031/001412 · approved 31 Oct 2017
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/240626/008750 · Approved
- Building plan approvedBDA - Bangalore Development Authority · BDA/EM/EO-05/TA-4/E/74/2025-26 · 6 Mar 2026
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBoreWell,Local Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
131 files on the RERA page: Approved plan ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q1 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
| Q2 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station1.87 kmReliable
- Nearest railway station1.72 kmReliable
- Bus stops within 500 m3Caveat
Parks, shops, daily needs
- Supermarkets within 1 km4Caveat
- Parks within 1 km8Caveat
- Nearest lake / water body (≥2 ha)1.39 kmCaveat
Hospitals
- Nearest hospital0.56 kmCaveat
Schools
- Schools in pincode 560067 (UDISE+ census)57Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km9Caveat
- Median pupil-teacher ratio, schools within 1 km24.1 :1Caveat
- Schools with library + playground + ICT lab (1 km)7Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionKadugodi PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well60.8 m below groundCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)8.55 kmReliable
- Nearest sewage treatment plant2.24 kmCaveat
- Industrial zones within 1 km1Caveat
- Nearest airfield runway (any, incl. military)5.08 kmCaveat
- Nearest commercial-airport runway20.02 kmReliable
- Distance to runway approach-path proxy18.43 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (13.01182, 77.76340), 2026-10-24. Each figure's source and caveat are in the full report.